The resistance properties of each mat must now be checked. It is essential
that this step is done thoroughly as required throughout the installation.
02
Installation Preparations
2.3
Use a high-quality digital ohmmeter or multimeter to make the required mea-
surements. Measure the resistance between the white (or red for 240 VAC)
lead and the black lead. Check that the measurement is within the range listed
on the table at page 29.
Record these values in the system information table. If resistances are
measured slightly below the rated value, it might be due to low air tem-
perature or meter calibration. Contact Warmset if in doubt.
The system should also be checked for short circuits. Measure the white (or
red for 240 VAC) lead to ground (green and yellow), and black lead to ground.
Both of these measurements should read no continuity. Some meters display
this as ‘in
fi
nite’ ohms or ‘open-line’.
These steps are performed three times in the installation process.
It is very important that they are performed accurately each time.
If there is any inconsistency in the readings, make note of the values and
contact the manufacturer. This could indicate possible damage to the system.
A
D
C
B
E
A.
White (or red for
240 VAC)
B.
Black
C.
Ground Lead
(green & yellow)
D.
Black Wire:
to COM
E.
Red Wire:
to OHM
Resistance
<
Insulation
<