Modular end termination

(TT-MET-PC)

TT1100-OHP

water sensing cable

TT1100-OHP

water sensing 

cable

Modular branching connector

(TT-MBC-PC)

Modular leader cable

(TT-MLC-PC)

Modular jumper cable

(TT-MJC-xxx-PC)

Note:

•  Drawing not to scale.

Modular jumper cable

(TT-MJC-xxx-PC)

Modular end termination

(TT-MET-PC)

TraceTek alarm 

module (several 

models available;

TTDM-128 alarm and

locating module 

is shown)

complete system connections and layout

A.  TT1100-OHP is available in a variety of pre-cut and terminated 

lengths. Each cable has a female plastic connector on one 

end and a male plastic connector on the opposite end. Cable 

sections plug together like extension cords.

B.  (Optional) A branch connector (TT-MBC-PC) is used to connect 

and branch “T” lines. The branch connector has one male 

connector and two female connectors. For mapping purposes, 

the cable connected to the center leg of the branch connector 

will be counted first, then the distance measurements will 

continue from the second female connector and continue along 

the rest of the system. A dead band of 15 ft (5 m) is inserted 

at the beginning and end of each branch to avoid any location 

ambiguity.

C.  (Optional) It is permissible to have TT-MBCs installed on 

branches as needed to fully trace a pipe system.

D.  Install an end termination (TT-MET-PC) at the end of the main 

line and each branch line. (Note: A good check on the system 

design and bill of materials is that the total number of end 

terminations installed in the system should equal the number 

of branch connectors plus one)

E.  (Optional) Install jumper cables (TT-MJC-xxx-PC) as needed to 

connect sensing cable sections if they are spatially separated. 

Jumper cable is available in various pre-cut and terminated 

lengths and is also available in bulk form for long distance runs 

between the sensor cable and the instrumentation point.

F. Install a leader cable (TT-MLC-PC) between the sensor cable 

and the monitoring instrument. The factory standard length 

of leader cable is 12 ft (4 m). It has a female plastic connector 

on one end and four tinned leads on the opposite end for 

connection at the instrument’s sensor cable terminal block. In 

some installations the distance between the instrument and the 

start of the sensor cable run will be much greater than 12 feet. 

In those cases a simple solution is to purchase a jumper cable 

of sufficient length, then cut off and discard the male connector 

and any extra cable. Bulk jumper cable and connector kits are 

also available for lengths that exceed the longest available pre-

cut jumper cable.

G.  Use tie-wraps to neatly coil and secure any excess sensor 

cable, jumper cable, branch connectors, etc.

Summary of Contents for TraceTek TT1100-OHP

Page 1: ...esigned for testing and troubleshooting TraceTek systems Digital multimeter Can be used as an alternative or supplement to the PTB Meter must have 20 MΩ range TT MAPPING CAP PC PN P000000872 Used to simulate leaks at connector points during commissioning and mapping process Extra TT MLC PC PN 683262 000 Leader cable Used with the ohmmeter to make easier connections to the sensor cable for resistan...

Page 2: ...here hold down clips will be placed so adhesive can work properly Position hold down clips so the sensing cable will provide the desired leak detection coverage To best secure the cable alternate the direction of the hold down clips and install them at intervals of no greater than 6 feet 2 m and at every change in direction at sides of trench for example Important Let the adhesive dry per manufact...

Page 3: ...ps off the bottom of the pipe or fitting Do not install the cable on the top or side surface of a pipe Do not spiral the cable on horizontal pipe Exception If the cable is used to trace vertical pipe the cable should be spiraled around the pipe and secured with tie wraps B For sumps containment trenches and subfloor applications Pull the cable alongside the installed hold down clips minimum bend r...

Page 4: ...ing Cable Test Procedure 3 Connect the sensing circuit to the TraceTek alarm module and activate the system as soon as is practical Use the alarm module to monitor the sensing cable during the final stages of construction Take precautions if installation is incomplete at end of work day At the end of the work day Ensure that there are no open connectors Each sensing cable should be connected to a ...

Page 5: ...A use the PTB to locate the liquid or contamination and take appropriate corrective action Method with Ohmmeter 1 Ensure the end termination is connected to the sensing cable If checking several lengths of sensing cable in series a cable string ensure they are all connected 2 Connect a Modular Leader Cable TT MLC PC to the sensing cable 3 Verify that the sensing cable is intact Loop 1 Measure the ...

Page 6: ...e to have TT MBCs installed on branches as needed to fully trace a pipe system D Install an end termination TT MET PC at the end of the main line and each branch line Note A good check on the system design and bill of materials is that the total number of end terminations installed in the system should equal the number of branch connectors plus one E Optional Install jumper cables TT MJC xxx PC as...

Page 7: ...a channel number and display the words SYSTEM NORMAL If the Yellow LED is on in any of these instruments or the words Cable Break or Loop Break is displayed then the cable system must be inspected for loose connections missing end terminations until the cable continuity is established and the Normal condition is achieved LEAK testing can be done with a mapping cap TT MAPPING CAP PC The MAPPING CAP...

Page 8: ...uced for a new leak Yellow LED visible on TTC 1 TTSIM 1A TTSIM 2 or flashing yellow LED on TTSIM 1 Could be cable break or service indication Refer to alarm module instructions for more infor mation For Cable break indication Check for loose connectors missing end terminations broken jumper wires or physical dam age to the cable Repair or replace cable if necessary The TT MET PC end termination ca...