3 SECTOR TIE BACK PIPE INSTALLATION
ADDITIONAL
SECTORS HIDDEN
DETAIL R
3 SECTOR TIE BACK PIPE INSTALLATION
A
A
B
B
DETAIL T
LEG BRACKET ATTACHMENT
TRIM EXCESS OFF
TIE BACK PIPE
CROSSOVER PLATE
1/2" X 2-9/16" U-BOLT KIT
5/8" X 2" BOLT KIT
DETAIL S
FRAME ATTACHMENT
5/8" X 4" BOLT KIT
END PLATE
1/2" X 1-1/2"
BOLT KIT
INSTALLING TIE BACK PIPES FOR 3 SECTOR INSTALLATION
Note:
This step is for (3) Sector installations only. For Single Sector installations, see Step 6B. Before installing Tie Back
Pipes, all (3) Sectors must be installed on tower legs.
Attach Tie Back Pipe to the face of the Frame using (1) Stiff Arm End Plate, (1) 1/2" x 1-1/2" Bolt Kit, and (1) 5/8" x 4" Bolt
Kit. Attach Tie Back Pipe to the Leg Bracket of the adjacent Sector Frame using (1) Stiff Arm Crossover Plate, (2) 1/2" x 2-
9/16" U-Bolt Kits, and (1) 5/8" x 2" Bolt Kit. Tie Back Pipes may be attached to top side or bottom side of adjacent leg
bracket. Trim excess Tie Back Pipe 12" past the leg attachment point. Apply (3) coats Zinga to all field cut and drilled
surfaces. Repeat for additional stiff arm.
NOTE: TIE BACK PIPES MUST BE INSTALLED ON OPPOSITE CORNERS OF FRAME (LOCATIONS A-A OR B-B). DO
NOT INSTALL TIE BACK PIPE IN AN A-B CONFIGURATION.