5.1.2 Preparing gas inlet system
Fig. 9:
Correct alignment on the flange of the QMA with C/B ion source
Procedure
► Prepare the gas inlet system as necessary to enable easy connection to the ion source afterward.
► Mark the correct alignment (arrow direction) on the flange of the QMA and of the system, if the
crossbeam ion source has to be aligned to the gas supply.
5.1.3 Installing support plate
Required tools
● Screwdriver,
no. 6
1
2
Fig. 10:
Installing support plate
1 Clamping screw on the side
2
Support
Procedure
1. Place the analyzer on the edge of the table.
2. Use the screwdriver to loosen the clamping screw on the side of the support plate.
3. Push the support plate onto the analyzer flange.
4. Align the support plate in such a way that you are able to easily hold the analyzer to guide it into
the vacuum system with the correct orientation.
5. Tighten the clamping screw with the screwdriver.
Installation
27/52