CAYMAN Part 2 Overview – Operation - Spare parts lists
Action in case of power cut
2017-03-22
49
Fig. 72: Manual
pump
Fig. 73: Push
button ”ON /
OFF”
9. Turn the selector switch to position “3” (Manual pump) (
Fig. 72)
.
10. Pump the water from the pump container till clean water come
out at the mortar hose connection.
11. Switch the machine off by pressing the red push button control
voltage “OFF” (
Fig. 73)
.
12. Open quick closures and drain the residual water from the
pump container.
13. Close the quick closures again.
14. Briefly switch the machine on by pressing the green push
button control voltage “ON” so that the residual water is
pumped out of the pump (in case of risk of frost also).
37.7 Installing the cleaned mixing tube
Fig. 74: Installing the mixer
NOTE!
While installing, take care that you are clean and
dry.
Pay attention to the correct fit of metering and
mixing shaft.
Always keep the quick closures and seals clean.
Grease the bearing journal and connecting pieces
of the mixing shaft.
38 Action in case of power cut
Fig. 75: “ON / OFF” -Push button
NOTE!
The CAYMAN is equipped with a restart interlock. In
case of a power cut, the system must be restarted
by pressing the green push button control voltage
“ON”.
NOTE!
The mortar hoses must be cleaned immediately in
case of a longer power failure.
Before opening the couplings ensure that there is
no more pressure on the hoses (observe display at
mortar pressure gauge)!
Summary of Contents for 00 24 88 94
Page 83: ...CAYMAN Part 2 Overview Operation Spare parts lists Circuit diagrams 2017 03 22 83 ...
Page 84: ...CAYMAN Part 2 Overview Operation Spare parts lists Circuit diagrams 84 2017 03 22 ...
Page 85: ...CAYMAN Part 2 Overview Operation Spare parts lists Circuit diagrams 2017 03 22 85 ...
Page 86: ...CAYMAN Part 2 Overview Operation Spare parts lists Circuit diagrams 86 2017 03 22 ...
Page 87: ...CAYMAN Part 2 Overview Operation Spare parts lists Circuit diagrams 2017 03 22 87 ...
Page 88: ...CAYMAN Part 2 Overview Operation Spare parts lists Circuit diagrams 88 2017 03 22 ...
Page 89: ...CAYMAN Part 2 Overview Operation Spare parts lists Circuit diagrams 2017 03 22 89 ...
Page 90: ...CAYMAN Part 2 Overview Operation Spare parts lists Circuit diagrams 90 2017 03 22 ...
Page 91: ...CAYMAN Part 2 Overview Operation Spare parts lists Circuit diagrams 2017 03 22 91 ...
Page 93: ...CAYMAN Part 2 Overview Operation Spare parts lists Circuit diagrams 2017 03 22 93 ...
Page 94: ...CAYMAN Part 2 Overview Operation Spare parts lists Circuit diagrams 94 2017 03 22 ...
Page 95: ...CAYMAN Part 2 Overview Operation Spare parts lists Circuit diagrams 2017 03 22 95 ...
Page 99: ...CAYMAN Part 2 Overview Operation Spare parts lists 2017 03 22 99 ...