SWING M delivery pump / Part 2 Overview, operation and service
Operation
5.5
Putting the machine into operation
5.5.1
Avoid hose clogging
1
Figure 29: Unscrew the nozzle
To avoid the hose clogging, the nozzle (1) must be
unscrewed from the spray gun before spraying for the first
time!
5.5.2
Feeding material to the machine
4
1
7
3
2
5
6
Figure 30: Switching on
1. Turn the pump motor selector switch (1) to "right" position.
2. Switch the machine on by pressing the green pushbutton (2)
control voltage "ON".
Green control lamp (3) lights up.
3. Adjust the amount of material on the potentiometer (4).
4. The machine can be switched on and off via the remote control
cable (5).
5. When working with dummy plug (6), the machine starts immedi-
ately.
8
9
Figure 31: Open the ball valve
6. Open the ball valve (8) on the spray gun.
7. Run the machine until material comes out of the spray gun, then
close the ball valve (8) again.
8. Switch off the machine via the remote control cable or the red
pushbutton (7) control voltage "OFF".
9. Screw the nozzle (9) back onto the spray gun.
The correct mortar consistency is reached, if the material
mixes on the surface to be sprayed (we recommend appli-
cation on wall surfaces from top to bottom).
5.5.3
Potentiometer
1
Figure 32: Potentiometer
1. The amount of material to be sprayed can be regulated via the
potentiometer (1).
page 28 / 52