Mixing pump G 4 X FU 230/400V / Part 2 Overview, operation and service
Maintenance
6.6
Actions after completed maintenance
After finishing the maintenance works and prior to switching on the
machine, the following steps have to be carried out:
1. Check all previously loosened screw connections for secure fit.
2. Check if all previously removed safety systems and covers are
properly reinstalled.
3. Ensure that all tools, materials and other equipment used have
been removed from the work area.
4. Clean the work area and remove any spilled materials such as
liquids, processing material or similar.
5. Ensure that all safety systems of the installation work perfectly.
6.7
Periodic inspection/expert inspection
Construction machinery has to be inspected for safe working
condition in accordance with the operating conditions and the oper-
ational requirements as needed, however at least once a year by
an expert.
Pressure vessels have to undergo the prescribed expert inspec-
tions.
The inspection results have to be documented and kept at least
until the next inspection.
DOCUMENT CENTRE
The documents for the expert inspection can be found on the
internet at www.pft.net.
Open the Document Centre under Service → Downloads.
In this area, select the expert inspection category to access all rele-
vant inspection documents.
6.8
Spare parts lists
DOCUMENT CENTRE
The spare parts lists for the machine can be found on the Internet at
Open the Document Centre under Service → Downloads.
In this area, select the spare parts list category.
In addition, select the machine you are looking for.
page 72 / 80
Summary of Contents for 00260621
Page 77: ...Mixing pump G 4 X FU 230 400V Part 2 Overview operation and service Disposal page 77 80...
Page 78: ...Mixing pump G 4 X FU 230 400V Part 2 Overview operation and service Disposal page 78 80...
Page 79: ...Mixing pump G 4 X FU 230 400V Part 2 Overview operation and service Disposal page 79 80...