PFT levelling pin / Safety, overview, operation and service
Operation
4.2
Inspection by machine operator
Prior to each shift, the machine operator has to examine the effec-
tiveness of the control and safety devices, as well as the proper
fitting of the protection devices.
The safe working condition of construction machinery has to be
checked by the machine operator during operation.
If the safety devices show any defects or if any other defects are
detected that compromise a safe operation, the supervisor has to
be informed immediately.
In case of defects that cause harm to persons, the operation of the
construction machine has to be stopped to eliminate the defects.
4.3
Setting up the levelling pin
4.3.1
Setting up basic device
1
0
0
cm
1
2
Figure 4: Setting up levelling pin
1. Remove the levelling pin from the transport box.
2. Place the device at the levelling starting point.
3. Unwind the measuring hose and lay it out without kinks.
4. Loosen the top locking screw (1) on the basic device.
5. Pull out the top part of the basic device (2) to a height of about 100
cm (centre of the liquid tank).
6. Moderately tighten the locking screw (1) again.