FERRO 100 II Part 2 Overview – Operation - Spare parts lists
Cleaning the machine and pump container
44
2018-03-26
Fig. 68: Cleaning the pump container
Use water jet to free the machine and pump material container
from adhering residual floating screed.
Fig. 69: Cleaning nozzles
Open the butterfly valve and drain off remaining water.
Close the butterfly valve and partially fill the pump material
container with water.
Fig. 70:
Installing mixing tube
Mount mixing tube on the dry material container.
NOTE!
While installing the parts, ensure that they are
clean and dry.
Pay attention to the correct fit of metering and
mixing shaft.
Always keep the quick closures and gaskets clean.
Grease the bearing journal and connecting pieces
of the mixing shaft.
Fig. 71:
Emptying the pump container
Turn the selector switch to position “4” (Manual pump).
Pump residual water out of the pump container.
Open the butterfly valve again and drain the residual water.
Subsequently, allow the pump to run dry for 2-3 seconds to drain
residual water from the pump.
NOTE!
After the end of work, the power supply and the
water supply must be disconnected from the
machine.