Procedures at End of Work and Cleaning
Version 02.2003
____________________________________________________________________________________________________________
_______________________________________________________________________________________
Knauf PFT GmbH & Co.KG
Telefon
09323 / 31-760
Postfach 60
Telefax
09323 / 31-770
D-97343 Iphofen
info@pft-iphofen.de
_______________________________________________________________________________________
WARNING!
Assembly and maintenance tasks should only take place when the machine has been
switched off completely. Disconnect the machine from the electrical mains.
On a regular working day, clean the HM 6 only once at the end of operation.
Cleaning should take place in the following 3 steps:
1. When you finish work close the butterfly valve.
2. Let the system run till clean water is coming out (approx. 2 min)
3. Clean the hopper on the outside with a brush or dry mop. Use water to clean the
hopper
only
when it is
empty
.
4. Clean the hopper on the outside with a brush or dry mop. Use water to clean the
hopper
only
when it is
empty
.
WARNING!
No water should enter the bearings or electrical parts ( plug, main switch, motor con-
nections box).
While assembling cleaned parts, make sure they are really dry and clean. Connect
mixing shaft to dosing shaft.
WARNING!
Keep all snap locks and seals clean. Grease bearing tang and connectors regularily.
At subzero temperatures release all water!