PFT Horizontal Screw Mixer LOTUS XS Overview – Operation
Dealing with a power failure
2019-11-07
33
29 Dealing with a power failure
1
Fig. 46: Power failure
Following a power failure, the machine can be started up again by
pressing the pressure switch “ON” (1).
NOTE!
Generally, the setting times of the materials to be
processed must be observed:
Clean the mixing tube as appropriate for the setting
time of the material and the length of the interruption
(take outdoor temperature into account).
30 Dealing with a water supply failure
NOTE!
The machine can be supplied with clean water from a
container using an inlet strainer (item number 00136619)
(see page 22, fig. 30 & 31).
31 Maintenance
31.1 Safety
Personnel
Unless otherwise stated, the maintenance work detailed here can be
carried out by the machine operator.
Some tasks may only be carried out by specially trained personnel or
only by the manufacturer.
Work on electrical systems must always only be carried out by
qualified electricians.
Basic information
WARNING!
Danger of injury due to improperly performed
maintenance work!
Improper maintenance can lead to serious injuries or
equipment damage.
Therefore:
– Ensure there is sufficient space to carry out the work
before beginning.
– Keep the work area clean and tidy. Unattached
components or tools left lying around or stacked on
one another can cause accidents.
- If components have been previously removed, ensure
that they are mounted again correctly, reattach all
fastening elements and adhere to the specified screw
tightening torques.