Mixing Pump RITMO XL FU 230/400 reversible Overview – Operation
Maintenance jobs
2019-05-13
61
49.4
Checking the pressure switch
49.4.1 Water pressure switch
Fig. 101: Pressure switch water
Pressure switch
Water (1)
Machine switches “ON”
Machine switches
“OFF”
Water
2,2 bar
1.9 bar
49.5 Air pressure switch
Fig. 102: Pressure switch air
Machine switches “ON”
Machine switches
“OFF”
Air
0,9 bar
1,2 bar
Fig. 103: Pressure switch
Switch compressor
on
Switch compressor
off
Compressor
2,4 bar
3,2 bar
See PFT air compressor DELTA 2 230V with pressure switch off
Article number of operating instructions: 00 19 96 67
49.6 Measures after maintenance
After completion of maintenance jobs, perform the following
steps before activation:
1. Check to ensure that all the loosened screw connections
are stable.
2. Check whether all the safety devices and covers removed
earlier are re-installed properly.
3. Ensure that all the used tools, materials and other
equipment have been removed from the work area.
4. Clean the work area and remove possible discharged
substances such as e.g., liquids, processing material etc.
5. Ensure that all safety devices of the system function
smoothly.