12
INSTALLATION
1.
Removing the packaging materials and tapes
Remove all transportation packaging materials and tapes. Open the doors and ventilate the unit. If the
outside panels are dirty, clean them with a diluted neutral dishwashing detergent. (Undiluted detergent
can damage the plastic components. For the dilution, refer to the instruction of the detergent.) After
the cleaning with the diluted detergent, always wipe it off with a wet cloth. Then wipe off the panels with
a dry cloth.
Note:
Remove the cable tie banding the power supply cord.
Prolonged banding may cause the corrosion of the cord
coating.
2.
Adjusting the leveling foot
Extend the leveling feet by rotating them as shown in
the figure until the front casters are separate from the
floor. Ensure the unit is level.
3.
Keeping the space (MDF-MU500H only)
Keep the adequate space at the back of the unit by using
the spacer on the back. To fix the spacer, follow the
procedure below.
- Press the spacer to the condenser.
- Pull up the lower edge to the horizontal position.
- Push in the spacer between the condenser.
4.
Fixing the unit
Two fixtures are attached to the rear of the frame. Fix
the frame to the wall with these fixtures and rope or
chain.
5.
Ground (earth)
The ground (earth) is for preventing the electric shock in the case of the electrical insulation is somehow
degraded. Always ground the unit at the time of installation.
WARNING
Use a power supply outlet with ground (earth)
to prevent electric shock. If the power supply outlet is
not grounded, it is necessary to install a ground by qualified engineers.
Never ground the unit through a gas pipe, water main, telephone line or lightning rod.
Such
grounding may cause electric shock in the case of an incomplete circuit.
Leveling foot
Spacer
Summary of Contents for MDF-MU300H
Page 2: ......