Installation
8-32
CardioMD Service Manual
1MAN0158-H11 04-2005 CSIP Level 1
8.3.3.6
Transporting the Gantry to the Installation Room
Note
. If the corridor has a 90° corner, the corridor width must be at least 42” (105 cm). See Figure
8.18. The gantry on its dolly with the jack beams mounted can go through 91 cm (36”) doorways.
Without the jack beams, the gantry can pass a doorway of 75 cm (30”).
Figure 8.18 Passage clearance for gantry
Procedure Details
1.
Roll the gantry in position over the
anchors holes.
2.
If the jack beams have been removed,
remount these now.
3.
Jack up and dismount the dolly wheels.
Summary of Contents for CARDIOMD
Page 1: ...CARDIOMD SERVICE MANUAL 1MAN0158 H11 04 2005 CSIP Level 1 ...
Page 10: ...Introduction x CardioMD Service Manual 1MAN0158 H11 04 2005 CSIP Level 1 ...
Page 16: ...Safe Operating Practices 1 6 CardioMD Service Manual 1MAN0158 H11 04 2005 CSIP Level 1 ...
Page 164: ...Detector Calibration Files 5 60 CardioMD Service Manual 1MAN0158 H11 04 2005 CSIP Level 1 ...
Page 328: ...Installation Procedures 9 38 CardioMD Service Manual 1MAN0158 H11 04 2005 CSIP Level 1 ...
Page 348: ...Planned Maintenance Procedures 11 6 CardioMD Service Manual 1MAN0158 H11 04 2005 CSIP Level 1 ...
Page 465: ......