Commissioning and functional test
5981_en_06
PHOENIX CONTACT
55
8
Commissioning and functional test
The field multiplexer system functions autonomously. The automatic startup of the system,
with its comprehensive selftest routines and automatic data assignment, eliminates the
need for time-consuming system configurations and avoids sources of error.
Commissioning is therefore very easy.
8.1
Checking the installation
The following points should be checked before the system is switched on, or if an error
occurs:
If all of these points have been checked, the voltage supply of the field multiplexer system
can be switched on.
Table 8-1
Checking the installation
Step
Reference to documentation
1.
Are all the Inline terminals approved for use
in the field multiplexer system?
Section “Devices permitted in a field
multiplexer station” on page 43
2
Is the assignment of the terminals correct
(complementary arrangement)?
3
Are all the system limits observed?
Section “Checking the system limits” on
4
Are the field multiplexer stations correctly
configured (master/slave, copper/fiber
optic)?
Section “Connecting and configuring
the field multiplexer” on page 53
5
If any interface converters are connected,
are they ready-to-operate?
6
Has the wiring of the power
supply/supplies for the field multiplexer
and all other terminals been installed
correctly?
7
Are all the sensors and actuators
connected correctly to the I/O terminals?
Terminal-specific data sheets
Summary of Contents for 2861205
Page 1: ...User manual Configuring and installing the Inline field multiplexer...
Page 6: ...IB IL 24 MUX MA PAC 6 PHOENIX CONTACT 5981_en_06...
Page 26: ...IB IL 24 MUX MA PAC 26 PHOENIX CONTACT 5981_en_06...
Page 64: ...IB IL 24 MUX MA PAC 64 PHOENIX CONTACT 5981_en_06...
Page 86: ...IB IL 24 MUX MA PAC 86 PHOENIX CONTACT 5981_en_06...