Note: 2U of space is reserved above the PDUs for cable routing. The number
and type of PDUs depends on the power service. If more PDUs are needed, or
when you need to add additional components into the rack (such as adding
another Slammer), then everything has to move up to make room, keeping the
2U of reserved space, and moving any Bricks displaced at the top to the next rack.
Related concepts
•
About Component Placement for Two or Three Slammers and FC Bricks
•
About Component Placement for Four Slammers and 64 Bricks
Related references
•
Cabling Practices for the Pillar Axiom 600 System
Related tasks
•
About Component Placement for Two or Three Slammers and FC Bricks
Pillar Axiom 600 systems with two or three Slammers support up to 32 FC Bricks.
Note: This topic applies only to Pillar Axiom 600 systems.
Install the hardware components in the rack as shown in the following figure. This
figure illustrates how the Pillar Axiom 600 system components are mapped into
fully loaded 42U racks for the following configuration:
● 1 Pilot
● 3 Slammers
● 32 FC Bricks
Chapter 2 Set Up the Rack
About Component Placement
45