PROPELLER DEICING SYTEM (Cont.)
H. DEICER BLADES (Cont.)
(3) REPAIR OF DEICER LEAD STRAP (Refer to figure 13)
Use B.F. Goodrich Field Repair Kit No. 77-802 which contains rubber patch material sufficient
for several repair jobs. Cements and solvents specified in these directions are not included in the
kit. (Abbreviation MEK in further steps stands for Methylethylketone.) Following steps apply
wherever cementing is specified in text:
(a) Clean area to be bonded or patched with MEK or acetone to remove all grease and dirt. It is
vital that surface be clean for good cementing job. After last wipe with cleaner, quickly wipe
surface with clean dry lint-free cloth to remove solvent film.
(b) Apply one even coat of 1300L cement (Minnesota Mining and Mfg. Co.) to area to be bonded
or patched and allow to dry (approximately one hour above 40F). Apply second even coat of
1300L cement and allow to dry.
(c) Cut the patch (.020 thick rubber to about 1/4 inch large on all sides of damaged area).
Protective paper is on side to be cemented. Apply masking tape on open side to prevent patch
from curling as cement dries; then strip off protective paper and apply 1300L cement in
smooth, even coat. Allow to air dry. After one hour, apply second coat and allow to air dry.
(d) With cemented surfaces either dry or with just a trace of tackiness, apply light coat of MEK
or Toluol over these surfaces to re-tackify and quickly complete the cementing job as directed.
Allow one hour to air dry before peeling off masking tape or mylar coating on air side. Rub
edges and center of patch to see that it is holding before releasing for flight. (Approximately
24 hours.)
– NOTE –
Do not touch cemented surface with dirty or oily fingers.
Repair of Lead Strap
Figure 13
PIPER AIRCRAFT
PA-32R-301/301T
MAINTENANCE MANUAL
30-60-00
Page 30-41
Reissued: July 1, 1993
2I11
Summary of Contents for PA-32R-301T SARATOGA S
Page 26: ...CHAPTER 4 AIRWORTHINESS LIMITATIONS 1C1 ...
Page 29: ...CHAPTER 5 TIME LIMITS MAINTENANCE CHECKS 1C4 ...
Page 53: ...CHAPTER 6 DIMENSIONS AND AREAS 1D6 ...
Page 64: ...CHAPTER 7 LIFTING AND SHORING 1D21 ...
Page 68: ...CHAPTER 8 LEVELING AND WEIGHING 1E1 ...
Page 72: ...CHAPTER 9 TOWING AND TAXIING 1E5 ...
Page 76: ...CHAPTER 10 PARKING AND MOORING 1E9 ...
Page 80: ...CHAPTER 11 REQUIRED PLACARDS 1E13 ...
Page 92: ...CHAPTER 12 SERVICING 1F1 ...
Page 126: ...CHAPTER 20 STANDARD PRACTICES AIRFRAME 1G17 ...
Page 127: ...THIS PAGE INTENTIONALLY LEFT BLANK ...
Page 139: ...CHAPTER 21 ENVIRONMENTAL SYSTEMS 1H5 ...
Page 188: ...CHAPTER 22 AUTOFLIGHT 1J7 ...
Page 193: ...CHAPTER 23 COMMUNICATIONS 1J12 ...
Page 203: ...CHAPTER 24 ELECTRICAL POWER 1J22 ...
Page 263: ...CHAPTER 25 EQUIPMENT FURNISHINGS 2A13 ...
Page 269: ...CHAPTER 27 FLIGHT CONTROLS 2A20 ...
Page 332: ...CHAPTER 28 FUEL 2D11 ...
Page 363: ...CHAPTER 29 HYDRAULIC POWER 2E18 ...
Page 404: ...CHAPTER 30 ICE AND RAIN PROTECTION 2G16 ...
Page 470: ...CHAPTER 32 LANDING GEAR 3A13 ...
Page 550: ...CHAPTER 33 LIGHTS 3D24 ...
Page 562: ...CHAPTER 34 NAVIGATION AND PITOT STATIC 3E12 ...
Page 582: ...CHAPTER 35 OXYGEN 3F8 ...
Page 604: ...CHAPTER 37 VACUUM 3G6 ...
Page 616: ...CHAPTER 39 3G18 ELECTRIC ELECTRONIC PANELS MULTIPURPOSE PARTS ...
Page 620: ...CHAPTER 51 STRUCTURES 3G22 ...
Page 636: ...CHAPTER 52 DOORS 3H14 ...
Page 650: ...CHAPTER 55 STABILIZERS 3I4 ...
Page 662: ...CHAPTER 56 WINDOWS 3I16 ...
Page 670: ...CHAPTER 57 WINGS 3I24 ...
Page 688: ...CHAPTER 61 PROPELLER 3J18 ...
Page 704: ...CHAPTER 70 STANDARD PRACTICES ENGINES 3K10 ...
Page 708: ...CHAPTER 71 POWER PLANT 3K14 ...
Page 737: ...CHAPTER 73 ENGINE FUEL SYSTEM 4A13 ...
Page 749: ...CHAPTER 74 IGNITION 4B1 ...
Page 783: ...CHAPTER 77 ENGINE INDICATING 4C11 ...
Page 793: ...CHAPTER 78 EXHAUST 4C21 ...
Page 801: ...CHAPTER 79 OIL 4D5 ...
Page 805: ...CHAPTER 80 STARTING 4D9 ...
Page 819: ...CHAPTER 81 TURBINES 4D23 ...
Page 833: ...CHAPTER 91 CHARTS WIRING DIAGRAMS 4E13 ...