ELECTRICAL INSTALLATION INSTRUCTIONS
WARNING:
Do not connect to power before installation is complete.
Always disconnect power to the ionizer before handling.
1.
All field wiring to be in accordance with NEC and Authorities Having
Jurisdiction (AHJ).
2.
Connect power to the ionizer using appropriate voltage per the following:
601(12V DC) 602 (24V AC) 603 (120V AC) 604 (208-240V AC)
See figure 3.
3.
For 120V AC and 230V AC models the installer shall provide a grounding
method per the local AHJ.
4.
For best results interlock ionizer with fan power.
5.
Apply power to unit. Confirm that green indicator light illuminates
indicating that the ionizer is functioning properly.
OPERATION
1.
When power is supplied to the ionizer, the ionizer will be activated and
the green ion indicator light will illuminate.
2.
The ionization unit is self balancing and does not require any type of
adjustment.
TROUBLESHOOTING
If the unit is not working, check the following:
1.
The supply fan is running and that the green light illuminates.
2.
Check the power input connections to the ionization unit. Verify all
connections are correct and tightened. Reconnect any loose wires as
necessary.
SEQUENCE OF OPERATION
1.
For units that are interlocked with the supply fan control, the BAS
controls the start/stop of the air conditioning unit supply fan.
FIGURE 3
PA600
IONIZER
(BLACK AC/RED DC)
(WHITE AC/BLACK DC)
FUSE
CONNECT
TO POWER