Instruction manual
KLD17-5/7-A
6/21
III. General assembly description
We ship the cage to a customer in partially assembled units. Extension arm with rollers and ratchet mechanism is
already installed in each cage pillar (item 1) (see drawing no. 1, 2 and 5). The cage construction consists of 9 pillars 5 m
high (item 1, drawing no. 1, 2 and 5). Pillars are fastened to anchors (item 2, drawing no. 1 and 2), which are
embedded in concrete according to the plan of the foundation blocks
–
drawing no. 3. The anchors should be
positioned in concrete in such a way that their hinges and arms face the throwing circle. Installed pillars constitute the
main structure of the cage which is ready for affixing the net and hoisting it.
Standard anchor, item 4
Extreme anchor, item 5
Central pillar, item 2
Extreme pillar, item 3
Horizontal stay, item 12
Bottom net tension cable, item 9
Net rim steel cable, item 8
Side arm, item 11
Rear pillar, item 1
Pillar arm with
guide roll
Hand crank
winch