1. PREPARATION OF FOUNDATION
►
Installation of stops
The gate movement must be controlled by stops fixed to the ground firmly to limit the extreme position of the gate.
►
Foundations
Screws to fasten the drive unit must be firmly
attached to the ground.
The foundation type and dimensions depend
on the type of ground.
The supply conductor must be laid according to
the standards concerning wiring systems and
effective in the country of use.
Successive stages
• Drive Unit location
• Installation of stops
• Foundations
►
Drive unit location
Horizontal setting
Pay attention to the fact that that the drive unit must be always within the area of the gate operation, during
both opening and closing.
Vertical
setting
The drive unit should be
located a little off the ground
(more than 20 mm).
Choose a suitable position for
the toothed bar. If necessary,
create a concrete base. It is
necessary to take into account
the gate position on trolleys.
250 mm mi
n
200 mm min
Gate
Foundation
Foundation
Toothed ba
r
Space for cables
Gate
Opening stop
Closing stop
75 do 80
Base
32
12
> 97
> 20
77
<100