12 CONTROL PANEL COMMISSIONING INSTRUCTIONS AND PROPER OPERATION
CHECKING AFTER INSTALLATION
The operations to be done before the control panel commissioning
:
•
detection, alarm, power supply lines preparation in accordance with the design;
•
installation of devices in the detection and alarm lines;
•
removal of the mains F3 fuse insert from the control panel terminal block;
•
the control panel assembly;
•
connection to appropriate terminal of all lines introduced to the control panel, with
exception of 230 V mains conductors;
•
creation of the paper insert with zone descriptions (and its location in the zone field on the
front panel)
•
preparation of the line elements list with their location description.
Electric connections inspection:
•
checking of the configuration jumpers positions on the control panel printed circuit board;
•
checking of correctness of line wires connection to the control panel terminals with special
attention to proper polarization (‘+’, ‘-‘)
•
inspection of end-of-line resistors connection in the last bases of the supervised lines
(detection and alarm ones);
•
in the case of unused lines (detection and alarm ones) – checking of end-of-line resistors
connection in the lines terminals in the control panel;
•
batteries insertion;
•
connecting in series two 12 V batteries with special attention given to ‘+’, ‘-‘ polarisation
marking on the battery clamps.
Commissioning
•
connection of the mains voltage and the PE wire.
ATTENTION! Dangerous voltage!
•
The control panel commissioning by inserting the F3 mains supply fuse insert;
•
readout of the faults revealed by the control panel and removal of possible discrepancies in
the circuits;
•
the control panel optimal configuration parameters setting using the functions described in
Table 4.3;
•
testing optical indicators on front panel;
•
testing all line elements (detectors, MCP, signalling devices and other equipment connected
to the system) paying attention to their real location consistence with the description in the
zone field;
•
checking operation of the executive devices interoperating with the control panel
•
testing alarm and fault signal transmission;
•
modification of the default access codes for the user codes (if necessary).
After the installation commissioning it is advised to check and possibly to set the current date and
time and the event memory erasure.
The works can be treated as finished when all actions described above have been performed and
proper operation of all system devices has been confirmed as well as the control panel operation in
the quiescent mode (without faults and disablements signalling) – the installation can be passed to
its user.