40
Roll-Up Curtain Installation – Part 2
To install the Vertical Tube (HT10020) that
supports the Roll-Up Unit (MV1000), drill a 5
diameter hole that is 8
in depth. The end of the
Vertical Tube that has a plate, goes into the hole.
The top of the Tube should extend 12
above
the upper wood rail. Backfill the hole and tamp
around the tube to compact the soil.
Place the Roll-Up Unit onto the Vertical Tube.
See illustration at right and Detail B.
To prepare the first Roll-Up Tube (CF1014), drill a
3/8
clearance hole in the non-swaged end of the
section. Place the Roll-Up Tube over the shaft on
the Roll-Up Unit and replace the screw and nut
that will hold this section in place.
Continue to add additional Roll-Up Tube sections
until you reach the other end of the FieldPro.
Secure the tube sections together at each splice
with 1/4
-14 x 1
Self-Drilling Screws (NB1809).
See Detail A.
Trim the last Roll-Up Tube flush with the End
Frame.
Use the marks previously placed on the Poly
Curtain to align Roll Up Tube(s).
Begin fastening the Poly Curtain to the assembled
Roll-Up Tube using a Tube Clip every 36
. Keep
the poly on the Roll-Up Tube straight by continu-
ing to line up the poly and tube with the place-
ment marks as you progress down the side of
the FieldPro. See Detail C.
Roll-Up Tube
CF1014
3/8
Clearance Hole
(Req’d.)
Roll-Up Unit
MV1000
1/4
-14 x 1
Self-Drilling
Screw NB1809
1
HT Gearbox
Vertical ( 70
)
HT1002
9
Grade
Top of Wood Rail
8
Deep
Hole
12
Top edge of Poly Curtain
Poly Curtain Panel
Marks placed on Poly
Detail A
Detail B
Detail C
Placement
Mark
Gearbox
Vertical Tube
HT1002
Roll-Up Unit
MV1000
Roll-Up Tube
CF1014
Tube Clip
Snap on
Tube Clips
(RC1010).
1
2
3
Instructions on this page apply
to 20
& 24
FieldPro Models