Automatic boiler for wood pellets
22
4
PLACEMENT OF THE PRODUCT IN BOILER ROOMS, PRINCIPLES OF
INSTALLATION
4.1
PLACEMENT OF PRODUCTS IN BOILER ROOMS
Minimum distances determine the space necessary to perform the operation and maintenance of the equipment. Boiler
must be placed on horizontal non-flammable material, which overlaps min. 10 cm over the platform of installed
equipment. Floor in front of the cleaning door has to be out of non-flammable material and min. 60 cm.
The necessary height over the boiler to the ceiling of the boiler room is approximately 450 mm (600mm with KP52S,
KP62S, KP82S) for cleaning of the boiler.
4.2
SAFE DISTANCE FROM COMBUSTIBLE MATERIAL
COMBUSTIBILITY GRADE OF MATERIALS:
Grade A – non- combustible: stone, concrete, bricks, plasters, etc.
Grade B – hardly combustible: inorganic insulation – rotoflex, glass wool, basalt insulation, wood wool slabs, etc.
Grade C1 – low combustible: Formica, versalit, fibreboard, hardwood (beech, oak).
Grade C2 – moderately combustible: soft wood (spruce), chipboard, rubber, floor covering.
Grade C3 – easily combustible: asphalt, tar paper, PVC, paper --- etc.
Minimum safe distance from bulk flammable materials of the type B, C
1
and C
2
is 200 mm in course of installation of the
boiler (as well as during its operation).
This distance is double - i.e. 400 mm for easily combustible materials C
3
.
As regards relation to the electrical network – it is necessary to ensure that the wall socket where the boiler is connected
is always accessible.
4.3
LEGISLATION IN FORCE
Installed system is able to meet the installation requirements of Building Regulations in Northern Ireland (2010 No. 382).
Installed system is able to meet the installation requirements of Building Regulations in Wales (The Building Regulations
2010).
Installed system is able to meet the installation requirements of Building Regulations in Scotland [Building (Scotland) Act
2003 and the Building (Procedure) (Scotland) Regulations 2004.]
Installed system is able to meet the installation requirements of Building Regulations in England.
The product may only be installed by an organization trained by the manufacturer with authorization.
Electric parts may only be connected by an authorized person on professional competence in electrical engineering and
trained by a manufacturer.
Installation company or person installing the boiler has to adhere the following standards and
regulations,
apart from other things or your national equivalents.
4.3.1
Heating system and boiler
EN 12828 – Heating systems in buildings – Design for water-based heating systems
EN 303.5./2000 – boilers for central heating, part 5.
EN ISO 12100-2/2004 - structure and versions of boilers.
4.3.2
Venting
EN 1443 – Chimneys – general requirements 734200 (9/2004).
Pressure and temperature conditions necessary for safe operation of heat installations are described in the following
standards: EN 13 384-1 and EN 13 384-2.
Summary of Contents for KP 12S
Page 1: ......
Page 17: ...Automatic boiler for wood pellets 16 Picture No 9 Feeder F1 4 5 1 4 5 2 4 5 3 4 5 4 4 5 5 ...
Page 28: ...Automatic boiler for wood pellets 27 Picture No 20 Ceramic grate parts placement guide ...
Page 41: ...Automatic boiler for wood pellets 40 8 3 1 2 Menu users settings ...
Page 43: ...Automatic boiler for wood pellets 42 Cleaning an ash removing Skin Time window setting ...
Page 46: ...Automatic boiler for wood pellets 45 Actual values Configuration ...
Page 52: ...Automatic boiler for wood pellets 51 Cleaning Ash removing USB Time window setting ...
Page 53: ...Automatic boiler for wood pellets 52 Load from USB Save on USB ...
Page 58: ...Automatic boiler for wood pellets 57 ...
Page 60: ...Automatic boiler for wood pellets 59 ...
Page 61: ...Automatic boiler for wood pellets 60 i ...
Page 63: ...62 Picture No 24 Principle of the modulation ...
Page 64: ...63 Picture No 25 Directory information consumption wood pellets for boiler family KP ...
Page 65: ...64 Picture No 26 Circuit diagram control unit ...
Page 66: ...65 Picture No 27 Circuit diagram module HZS 533 ...
Page 67: ...66 Picture No 28 Circuit diagram HZS 533 HZS 535 ...
Page 73: ...72 11 APPENDIX 2 REPORT ON THE PUTTING THE BOILER KP INTO OPERATION ...
Page 74: ...73 12 APPENDIX 3 SELF ADHESIVE LABEL IMPORTANT SAFETY INFORMATION ...