1. 

WINCH/PULLEY LOCATION

.  Placements of the winch and hoist pulley are critical to ensure the proper and safe folding 

operation of the backstop.  Refer to the backstop installation drawing(s) provided with this project for all dimensional data 
parameters. 

 

A. 

When the unit is in the "UP" (stored) position, the cable tie-off at the mast must be directly below the pulley sheave.  Failure 
to do so will place additional lateral loads on the superstructure.  See Illustration 1. 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

B. 

The pulley is to be located on the 
exact centerline of the backstop 
mast as indicated on the backstop 
installation drawings.  Refer to 
Pages 26 and 27 in the Basketball 
Backstop Installation Manual for 
complete cable tie-off details. 

 

C. 

To avoid excessive wear on the 
pulley sheave and chafing of the 
cable against previous wraps on 
the drum, the sheave is ideally 
located on the centerline of the 
drum.  HOWEVER, if the cable 
does not wind evenly on the drum, 
the winch may be offset slightly 
from the sheave centerline to 
obtain an even wrap on the drum.  
See Illustration 2. 
 

2. 

SECURING CABLE TO THE WINCH DRUM

.  Route plain end of cable through hole in the 

winch drum and secure with set screw.  Note that cable must be taped before cutting to prevent the 
cable end from fraying.  Be sure to route cable in the 

UNDERWIND

 direction as detailed in 

Illustration 3.  

THERE MUST BE A MINIMUM OF THREE (3) WRAPS OF CABLE ON 

THE DRUM WITH THE BACKSTOP IN THE "DOWN" POSITION.

 

 
 
 

CORRECT

Illustration 1

WRONG !

WRONG !