12.0 Completion
© Baxi Heating UK Ltd 2012
12.1
Completion
1. Instruct the user in the operation of the boiler and
system explaining the operational sequence.
2. Set the central heating and hot water temperature
control knobs to the requirements of the user.
3. Carefully read and complete all sections of the
Benchmark Commissioning Checklist at the rear of this
publication that are relevant to the appliance and
installation. These details will be required in the event of
any warranty work. The publication must be handed to the
user for safe keeping and each subsequent regular service
visit recorded.
4. For IE, it is necessary to complete a “Declaration of
Conformity” to indicate compliance with I.S. 813. An
example of this is given in I.S. 813 “Domestic Gas
Installations”. This is in addition to the Benchmark
Commissioning Checklist.
5. Hand over the Users Operating and Installation and
Servicing Instructions, giving advice on the necessity of
regular servicing.
Fig. 72
Facia Panel
Case Front Panel