• Press button "info"
• Acknowledge selection with OK
• Adjust nominal value by using rotating knob
• Acknowledge setting with OK.
See alsosection Explanations for setting table.
6.7 Instruction of the customer
6.7.1 Instruction
The customer must be given full explanation of the heating plant operation and
functioning of the protective installations. It has to be pointed out especially:
- that the air inlet must not be closed or restricted;
- that the connection nozzle for the combustion air at the top of the device must
be accessible for the Maintenance engineer,
- Flammable materials and liquids must not be stored in the vicinity of the gas
boiler
- The customer has to carry out the following control checks himself>:
- Pressure check on the manometer (pressure gauge - 1 bar minimum);
- Check of the tundish under the blowpipe of the safety valve;
- Only approved heating engineer may carry out the inspection and cleaning work
annually.
6.7.2 Documents
- Asset ledger with check list of commissioning with legally binding signature for
the end user: Only components tested to the respective standard and marked
have been used. All components have been installed according to the maufac-
turer's instruction. The whole system conforms to the relevant standard.
Commissioning
7308272-03 03.14
Paramount three 30-115 kW
41
Summary of Contents for Paramount 40
Page 1: ...Installation manual Gas condensing boiler Paramount three 30 115 kW ...
Page 23: ...Prior to installation 7308272 03 03 14 Paramount three 30 115 kW 23 ...
Page 25: ...Fig 5 Connection plan Prior to installation 7308272 03 03 14 Paramount three 30 115 kW 25 ...
Page 28: ...4 9 Legend Prior to installation 28 Paramount three 30 115 kW 7308272 03 03 14 ...