Powered by Safety
®
36
Operation
01.4IB.51000C
PowlVac® Metal-Clad Switchgear
5kV & 15kV
The standard lift truck is used when adequate
aisle space (68” minimum) is available. Perform
the following steps to insert a circuit breaker in
the upper compartment:
1) Inserting the Circuit Breaker Into the Lower
Compartment (One-High Design)
Use the appropriate circuit breaker or
ground and test device instruction bulletin
in conjunction with this section to
insert/remove the element from the
switchgear compartment.
NOTICE
a. Verify that the circuit breaker
open/closed indicator displays
“BREAKER OPEN” and if not, press the
manual trip operator to open the circuit
breaker.
b. To insert the circuit breaker into the
lower circuit breaker compartment,
open the compartment door and align
the wheels with the floor pan channels
of the compartment. Verify that there
are no locks or tags on the circuit
breaker of the shutter interlock that
would block operation or indicate an
issue with the equipment and that the
floor pan channels are free of debris
prior to inserting the circuit breaker.
c. Roll the circuit breaker in the
compartment until the racking crank
arms make contact with the vertical
slots in the compartment. The
anti-rollout latch on the lower right side
of the circuit breaker will engage the
block in the compartment, preventing
accidental removal of the circuit breaker
from the compartment.
Note:
This is the disconnected position.
2) Inserting the Circuit Breaker Into the Upper
Compartment (Two-High Design)
Use the appropriate circuit breaker or
ground and test device instruction bulletin
in conjunction with this section to
insert/remove the element from the
switchgear compartment.
NOTICE
a. Verify that the circuit breaker
open/closed indicator displays
“BREAKER OPEN” and if not, press the
manual trip operator to open the circuit
breaker. Verify that there are no locks or
tags on the circuit breaker or the shutter
interlock that would block operation or
indicate an issue with the equipment
and that the floor pan channels are free
of debris prior to inserting the circuit
breaker.
b. To insert the circuit breaker into the
upper circuit breaker compartment a
lifting device is required (Figure 26).
If the aisle spacing is adequate, the
standard lift truck may be used (68”
of space is required). See
for specifications.
c. Lower the lift truck tray to the ground
and roll the circuit breaker onto the tray
until the anti-rollout latch engages with
the ramp on the tray (Figure 26, b).
d. Open the circuit breaker compartment
door and align the truck with the
opening. Raise the tray until the front of
the tray is slightly higher than the front
edge of the compartment (Figure 26, e).
e. Move the lift truck forward and align
the tabs on the front of the tray with
the cutouts in the circuit breaker
compartment (Figure 26, f). Lower the
tray until the tabs set in the cutouts.
Apply the brake on the lift truck.