On the control Panel there is also a Selector switch, which makes it possible to
select to operate either the left hoist, the right hoist, or both hoists. This will allow a
manual correction of the inclination of the platform. See Picture 2
A Green Pilot light will be illuminated when the power is connected correctly.
Change 2 phases in case pilot light does not come on when power plug is inserted
to correct the Phase sequence.
A Red Problem light will be illuminated in case of
1. Overloading of one of the hoists.
2. Emergency stop is pressed.
3. Thermal Protection of one of the hoists is activated.
4. Plugs of the hoists are not connected.
Note: On the right hand site of the CCB there is a selector switch to control the platform from a
Pendant control.
When the selector is in horizontal position control from the Central box and from the pendant are
enabled. When the selector is in vertical position, only controls from the central box are enabled.
The Pendant controlled is wired into the circuit after the automatic level control, so in case there
is a failure with the automatic level module, the normal control from the central box is prevented,
but it remains possible to control the platform with the Pendant. In that case the level of the
platform needs to be maintained by operating the brake on the hoists, if necessary.
NOTE: the emergency button on the Pendant will disable operations on the pendant as well as on
the CCB.
In Case of power failure the platform can be lowered by releasing the brake on the Titan
hoists manually.