15
4111-0044 — June 2021
© 2021 Systems, LLC
RCR w/Side Shift Installation (continued)
c. Weld on roller track stops (
K
, Figure 11) and
proceed to step 8.
8. Lube the rear hinge pins using grease. Install the
hinge pins (
C
) in one side of the rear embed hinge
tubes, leaving room for the platform hinge tubes.
9. Ensure maintenance props (
E
) are in the lowered
position and tightly secured.
10. Lower the dock leveler down, centering the
leveler’s hinge tubes with the carriage’s. While
lowering, take care to avoid damaging the hoist
cylinder rod ends.
11. Insert the hinge pins, working from the outside to
the inside. Install and secure cotter pins in hinge pins.
12. Complete all hydraulic connections.
Note:
Do not connect hoist cylinder(s) at this time.
System must be purged of air before connecting.
13. Proceed to “Install Control Panel and Wiring” on
Page 18.
Additional views of RCR w/Side Shift installation
are shown on pages 15-16.
A — Roller Track
B — Hoist Cylinder Pin
C — Rear Hinge Pin
D — Lifting Brackets
E — Maintenance Props
F — Carriage
G — Side Shift Cylinder Mount
H — Side Shift Cylinder
K — Roller Track Stop
Figure 11
Figure 12
Figure 13
INSTALLATION
E
TOLERANCES
(UNLESS OTHERWISE NOTED)
FRACTIONAL:
1/32"
DECIMAL:
.00 =
.01"
.000 =
.005"
ANGULAR:
1
DRAWN BY
CHECKED BY
DRAWING NO.
DATE
MGM
3/8/2018
S Y S T E M S, I N C.
L o a d i n g D o c k E q u i p m e n t
P O W E R A M P
M C G U I R E
D L M
This print is the property of Systems, Inc. and represents a proprietary article in which Systems, Inc. retains any and all patent and other rights, including exclusive rights
of use and/or manufacture and/or sale. Possession of this print does not convey any permission to reproduce, print or manufacture the article or articles shown therein,
such permission to be granted only by written authorization signed by an officer or other authorized agent of Systems,Inc. thereof.
MATERIAL
STOCK NO.
RR SIDE SHIFT
MANUAL
TOLERANCES
(UNLESS OTHERWISE NOTED)
FRACTIONAL:
1/32"
DECIMAL:
.00 =
.01"
.000 =
.005"
ANGULAR:
1
MATERIAL
DRAWN BY
CHECKED BY
DRAWING NO.
DATE
MarkS
9/23/2020
170381-ZD0
Side Shift RCR
FINAL ASSEMBLY, RAIL RAMP
P O W E R A M P
M C G U I R E
D L M
S Y S T E M S
L o a d i n g D o c k E q u i p m e n t
This print is the property of Systems, LLC and represents a proprietary article in which Systems, LLC retains any and all
patent and other rights, including exclusive rights of use and/or manufacture and/or sale. Possession of this print does
not convey any permission to reproduce, print or manufacture the article or articles shown therein, such permission to be
granted only by written authorization signed by an officer or other authorized agent of Systems, LLC thereof.
STOCK NO.
EASTERDAY FARMS, 50K
REV A - ECN 18-066
A
F
K
H
G
F
K
Summary of Contents for RCR Series
Page 25: ...23 4111 0044 June 2021 2021 Systems LLC OPERATION This page intentionally left blank ...
Page 38: ...36 4111 0044 June 2021 2021 Systems LLC PARTS Platform Hydraulic Hoses C A G F E D B H ...
Page 58: ...56 4111 0044 June 2021 2021 Systems LLC This page intentionally left blank MISCELLANEOUS ...