Prepare Pit
A—Distance (Pit Width)
(Front and Rear)
B— Distance (Dock Floor-to-Pit
Floor) (All Four Corners) 1/2”
Taper Rear to Front
C— Distance (Pit Length)
(Both Sides of Pit)
D— Distance (Pit Corner-to-Corner) (Top,
Bottom, and Both Sides)
Before lowering the dock leveler into the pit, the
following must be performed:
1. Remove all debris from the pit and sweep the pit
clean.
2. Check the entire dock leveler pit for proper
construction according to approved/certified
pit drawings. Make sure pit is square, has the
proper depth and taper by making the following
measurements:
• Measure pit width distance (A) at both front
and rear of pit.
• Measure dock floor-to-pit floor distance (B) on
both sides of the rear embed channel and at
front if applicable.
• Measure pit floor taper, rear to front cannot
exceed 1/2” total taper.
• Measure pit length distance (C) at both sides.
• Measure corner-to-corner (criss-cross) distance
(D) at both sides. Take measurements at dock
floor level and at pit floor level.
NOTE” If any measurement are off by more than
1/8 in. (3.18 mm) in depth, width and
squareness 1/4 in + 0 in (6.32mm) contact
Technical Services before proceeding.
3. Make sure the field junction box for the dock leveler
(E) and floor embed plate (F) is at the correct
location per pit diagrams.
Only trained installation professionals with the
proper equipment should install this product.
Post safety warnings and barricade the work area at
dock level and ground level to prevent unauthorized
use of the equipment before installation has been
completed.
B
A
C
B
C
A
D
F
E
Summary of Contents for VS series
Page 44: ...42 4111 0008 April 2017 June 2017 Centra Power Hydraulic Components PARTS A B E D F G I H C ...
Page 47: ...45 4111 0008 April 2017 June 2017 This page was left intentional left blank PARTS ...
Page 53: ...51 4111 0008 April 2017 June 2017 PARTS This page was left intentional left blank ...