Display
1
2
9
3
4
5
6
7
8
1)
Mains voltage sine wave cut in percent - represent the load of the building mains cables.
4% or more - poor wires or wires overload.
6% or more - a critical wiring condition.
2)
Sequencer on state indicator - Appears after Sequencer was started and next button press will lunch
sequencer turn off sequence.
3)
Voltage flicker - voltage pick fluctuation for one minute. High flicker can cause connected devices fault
even with normal voltage.
5V or higher - high stress to connected devices. May reduce life of the connected devices.
11V or more - there is a risk of damage to the connected devices. It is recommended to call
professional electrician for help
4)
Mains frequency - indicate the load of the national power system.
49,95Hz/ Гц or less
- heavy load.
49,90Hz/Гц
- power system critical situation.