2 - 1
3x3 UPS Installation
Issue 2 - November 2001
Chapter 2 - Installation
2.1 - Installation (Mechanical)
2.1.1 - Preliminary Checks
Before installing the UPS hardware the following preliminary checks must be carried out:
1.
Verify that the UPS room satisfies the environmental conditions stipulated in the equipment
specification, paying particular attention to the ambient temperature and air exchange
system.
Material admittance
1.
Remove any packaging debris, then visually examine the UPS and battery equipment for
transit damage, both internally and externally.
Report any such damage to the shipper immediately.
2.
Ascertain that the material supplied corresponds with that on the freight bill.
Identification
The equipment supplied is provided with an adhesive identification label placed on the UPS rear panel
reporting type of UPS model and power.
The cases used to transport the equipment must be unpacked as specified by the procedure stated
below.
Packing material removal
During this operation observe the indications (FRAGILE, UP) printed on the case to avoid damaging the
UPS
To remove the packing material proceed in the following manner:
1.
Place the equipment on the floor as instructed on the outer case (UP, DOWN).
2.
Cut the tape and open the flaps at the top of the cardĆboard box.
3.
Remove the extruded elements used as protective packing.
4.
Position the forks of the lifting truck under the UPS taking care not to damage the UPS
castors and lift it a few centimetres from the floor. Back up the forklift and position the UPS.
Lower to the floor.
Hinet is provided with wheels to allow ease of movement.
5.
Retain the packing material.
The original transit packing should be used if the equipment is be returned to the
maintenance centre, or moved to another position.
6.
Check that the equipment has not been damaged.
Any damage should immediately be reported to the Sales Representative.
7.
Locate the four battery fuses. Do not fit at this point.
8.
Locate the door key and panel bolt spanner secured on the rear of the UPS. Retain for future
use.
9.
The operator manual and communication cable are located behind the hinged front door.
Moving the cabinets
WARNING
Ensure that any lifting equipment used for moving the UPS cabinet has sufficient lifting caĆ
pacity.
Ensure that the UPS weight is within the designated surface weight loading (Kg/cm2) of any
handling equipment. See the UPS specification for weight details.
The UPS can be lifted using a fork lift. Take care when using either method not to damage
the UPS castors located on the bottom of the unit.