7
7. External battery terminal(Only available for long-run model)
8.Line Input circuit breaker (40K(L))
9.Maintenance bypass switch
10.Input/Output terminal
11.Power stage fan
12.Line Input circuit breaker (30K(L))
13.Output Grounding terminal
14.Output terminal: connect to mission-critical loads
15.Line input terminal
16.Input Grounding terminal
2-3. Single UPS Installation
Installation and wiring must be performed in accordance with the local electric laws/regulations and execute
the following instructions by professional personnel.
1)
Make sure the mains wire and breakers in the building are enough for the rated capacity of UPS to
avoid the hazards of electric shock or fire.
NOTE: Do not use the wall receptacle as the input power source for the UPS, as its rated current is less than
the UPS’s maximum input current. Otherwise the receptacle may be burned and destroyed.
2)
Switch off the mains switch in the building before installation.
3)
Turn off all the connected devices before connecting to the UPS.
4)
Prepare wires based on the following table:
Model
Wiring spec (AWG)
Input(Ph) Output(Ph)
Neutral
Battery
Ground
30K
8
8
4
4
30KL
8
8
4
4
4
40K
7
7
4
4
40KL
7
7
4
4
4
NOTE 1: The cable for 30K/30KL should be able to withstand over 63A current. It is recommended to
use AWG 8 or thicker wire for Phase and AWG 4 or thicker wire for Neutral for safety and efficiency.
NOTE 2: The cable for 40K/40KL should be able to withstand over 80A current. It is recommended to
use AWG 7 or thicker wire for Phase and AWG 4 or thicker wire for Neutral for safety and efficiency.
NOTE 3: The selections for color of wires should be followed by the local electrical laws and
regulations.
5)
Remove the terminal block cover on the rear panel of UPS. Then connect the wires according to the
following terminal block diagrams: (Connect the earth wire first when making wire connection. Disconnect
the earth wire last when making wire disconnection!)