11
Section VI Paralleled running
Diagram of the connection of paralleled running brake unit and inverter
(Only PB6032,PB6034 with this function
)
If 2 or more over brake units are paralleled, please refer to the above
diagram and connect the inverters, multiple brake units and brake resistors.
6-1
、
Host and slave select of function setting
(1)
The factory setting of the brake unit is set to be the host (M), do not
modify the factory setting if only one brake unit is used.
(2)
When 2 or more over brake units are paralleled, the control terminal
(S) is used. Please refer to the “Host and slave control connection”.
6-2
、
Host and slave control connection
(1)
The brake unit has host/slave switch. Set the brake unit 1 to be “M”,
the brake unit 2 and 3 to be “S”
(2)
Connect separately M1, M2 of the brake unit 1 with S1, S2 of the
brake unit 2;
Connect separately M1, M2 of the brake unit 2 with S1, S2 of the