3
INSTALLATION SITE
The driveway where the automatic barrier (boom gate) will be installed must
be previously analyzed, by checking the entire infrastructure of the place,
the floor conditions, the electrical network, the width of the passage span,
the height of the clearance (if any), the flow of vehicles and the need to use
optional accessories. That done, the equipment that best fits the needs of
the location should be chosen.
NOTE:
In driveways with low ceilings, the use of folding beams is generally
recommended. In this case, one must consult with the factory so that it can
provide one with the appropriate size beam for installing it on the specific
location.
IMPORTANT
One must check if there are any obstacles that may interfere with the
complete opening and closing of the beam.
If so, the installation of the equipment will be impaired, making it
necessary to repair the infrastructure of the site.
Carefully choose the model of the automatic barrier according to its
technical features and the location where it will be installed. Observe
the need for optional accessories. Calculate the flow of vehicles on
site.
NOTE:
If the floor does not meet the previous specifications, a concrete
plinth (foundation) must be provided for anchoring the cubicle, attending
to the dimensions its base. Generally, the concrete plinth should be 100
mm (~4 in) high above the floor level.
CONTENTS
Installation site .....................................................................................................................................3
General features ..................................................................................................................................5
Technical specifications .....................................................................................................................5
Equipment dimensions ......................................................................................................................6
Construction of the base for anchoring the cubicle ..................................................................7
Installing the automatic barrier .......................................................................................................8
Balancing the beam and checking the chain .............................................................................12
Adjusting the magnet bars .............................................................................................................13
Operation ...........................................................................................................................................14
TRIFLEX CONNECT BRUSHLESS Electronic Control Board ...................................................14
Encoder system (‘Reed Digital’) ....................................................................................................14