RBK 815 Recumbent Cycle
Page 46
Procedure 7.10 - Replacing the Secondary Axle Assembly
1.
Remove the top, rear, left and right covers per procedure 7.1.
2.
Loosen, but do not remove the idler pulley mounting nut.
3.
Remove tension from the primary belt by turning the primary belt tension
adjustment bolt counter-clockwise. See Diagram 7.4.
4.
Loosen, but do not remove the generator screws and tension bracket mounting
bolt, thread the tension adjustment bolt counter-clockwise to remove tension
from the secondary belt. See Diagram 7.13.
5.
Remove the secondary sheave per Procedure 7.8.
6.
Remove the secondary pulley per Procedure 7.9.
7.
Remove a second plastic washer from the secondary pulley side of the secondary
axle.
8.
Remove a retaining clip and from the secondary sheave side of the secondary
axle.
9.
Remove a large retaining clip from the secondary pulley side of the secondary
axle.
10. Remove the secondary axle from the frame and discard.
11.
Slide the replacement secondary axle into its mounting position in the frame.
Fasten the secondary axle with the large retaining clip removed in step 9. Inspect
the retaining clip to insure that it is securely snapped in.
12. Replace the retaining clip removed in step 8.
13. Slide a plastic washer, removed in step 7, onto the secondary pulley side of the
secondary axle.
14. Replace the secondary pulley per Procedure 7.9.
15. Replace the secondary sheave per procedure 7.8.
16. Tension the secondary belt per Procedure 5.2.
17. Tension the primary belt per Procedure 5.1.
18. Replace the covers per Procedure 7.1.