background image

INSTALLING THE AIR WIND TURBINE:

 

• 

Assembly blade set first using proper torque for 
hardware and provided tef

-

gel included.  AIR X 

Marine/AIR 30 units it is recomended tip to tip 
measurement of blades to avoid vibration.  Read 
AIR Owner

s Manual for procedure.

 

• 

All AIR turbines use a 1.5 inch SCH. 40/80 tower 
pipe (1.875 inch OD).  The YAW of the turbine 
slips into this size pipe with the YAW pad in place.  
Lift turbine 1/8 of an inch to isolate turbine on 
YAW pad to minimize vibration transfer from 
turbine to tower.

 

• 

Be sure all 3 WIRE connections (RED

-

BLACK

-

GREEN) are properly secure in tower pipe as non 
solid connections can lead to operational issues.

 

• 

After proper installation of HUB nut, secure nose 
cone on all 3 tabs on HUB.  Rotate blade set and 
listen for nose cone clicking or check any rubbing 
with HUB on FACE of AIR turbine.

 

• 

Prior to tower tilt up, power up turbine, be sure 
to check for the 2 LED blinks to assure the proper 
connection of turbine to battery.  Refer to AIR 
Owner

s Manual on this topic and LED operation.

 

AIR MAINTENANCE:

 

• 

Within 30

-

60 days after intial turbine install, 

check blade bolts, hub nut and YAW bolts for 
proper torque to ensure safe long term operation 
of the AIR unit.

 

• 

Every 6

-

12 months, repeat procedure inspection 

procedure of hardware and include the 
inspection of the Blade set for chips or nicks.  
Please refer to Maintenace section in AIR 
Owner

s Manual for specifcs on this topic.

 

Foam pack-

Blade

Nose 
cone in 

Nose cone & blade 

Hardware kit

 

AIR Wind Turbine:  Quick Start Guide –

 

Important Information

 

 

PROUDLY MADE IN THE  

USA

  

 

Primus Wind Power, Inc.

 

938 Quail Street 

 

Lakewood, CO 80215 USA 

 

Phone: 303.242.5820

 

info@primuswindpower.com

 

www.primuswindpower.com 

 

Reviews: