58
>>
RECTANGULAR POOLS
w
Use a hammer and a clamp to gently tap the slats into position if necessary. Do not
strike the wooden slats directly, use the protective brace (supplied). Be careful to
ensure that each row of slats is fully engaged before starting with the next.
>>
tHe woodeN walls (CoNt)
w
while assembling
the slats, make sure
as of the beginning
that the tongues
are fully engaged in
the grooves.
caUtion
w
Start by unrolling the strips of asphalt (fig.
13) that will insulate the wooden structure
from the concrete slab.
w
Lay out the ½ slats ‘8’ that make up the
pool widths, then at the corners fit them
into the slats marked ‘1’ that make up the
lengths (fig. 14).
w
The slats should be fixed to the metallic
posts as they are slotted into position
(these are predrilled) with screws 6x30 from
bag D.
w
After positioning the 1st layer of slats,
check that the diagonals are equal.
w
Screw the slats together using screws from
bag C as shown in fig 14.
w
Be careful to remove any splinters as you
go.
8
1
5x40
sachet C
figure 15
figure 13
figure 14
w
Fit together the remaining slats taking care that the slats machined to receive the
pool fittings are in their correct positions.
•
The slats with the openings for the return fittings should be in the 6th row.
•
The slats machined to take the skimmers should be placed in rows 9 and 10 for the
3x6 pools and rows 10 and 11 for 4x8 and 5x10 pools.
•
The slat that will hold the vacuum point should be in row 8 of the 3x6 pool or row 9
of the 4x8 and 5x10 pools.