6
Assembly and installation
User qualification, mechanical installation: trained qualified personnel, see
Chapter 2.3 ‘Users' qualifications’ on page 10
User qualification, electrical installation: Electrical technician, see
Chapter 2.3 ‘Users' qualifications’ on page 10
The system is fully factory pre-assembled. The cabling between the con‐
trol cabinet and the electrical power units is fully installed.
6.1 Assembly
WARNING!
High system weight
Possible consequence: Death or severe injuries, if the floor
cannot support the system and breaks.
Measure: Ensure that the floor of the installation site can
support the weight of both the empty and full system.
Selection of the installation site
The system must be easily accessible at all times for opera‐
tion, maintenance and filling.
Permissible ambient temperature: +5 °C to +40 °C.
Humidity: None. Rain and condensation not permitted.
Other: No dust, no direct sunlight.
6.2 Installation, hydraulic
CAUTION!
Possible environmental damage due to the polymer solution
is possible
Observe the safety data sheet for the polymer, as well as
statutory regulations for disposal when draining the drainage
lines and the overflow line.
Requirements:
n
The preparation water must be of drinking water quality and must be
free of solids and suspended particles
n
The inlet water pressure must be between 3 and 5 bar
n
The dimensioning of the process water, overflow and drainage lines
must be correct
Ambient conditions for operation