assigning an appropriate fuse in the fuse box).   The electrical system shall be made in accordance with applicable 
standards and regulations.  

 

2.2. Installation procedure. 

 

1. Before installation, cut off the voltage in the 230V power-supply circuit. 
2. Mount the PSU in a selected location and lead the connecting cables.  
3.  Connect  the  power  cables  (230V  AC)  to  L-N  terminals  of  the  PSU.  Connect  the  ground  wire  to  the  terminal 

marked with grounding symbol:

. Use a three-core cable (with a yellow and green PE  protection wire) to make 

the  connection.  The  power  cables  should  be  connected  to  the  appropriate  terminals  on  the  connection  board 
through the bushing.  

 

The shock protection circuit shall be done with a particular care: the yellow and green wire 

coat of  the  power  cable  should be connected to  the  terminal  marked  with  the  

  symbol  

in  the  PSU enclosure. Operation of the PSU without the properly made and fully operational 
shock  protection  circuit  is  UNACCEPTABLE!  It  can  cause  damage  to  the  equipment  or  an 
electric shock. 

 

 
 
4. Connect the power supply line and video signal to the BNC module (See Figure 4):  

- connect the supply voltage of the camera to the AUX1÷ AUX 4 outputs 
- connect the video signals from the cameras and the DVR to the BNC sockets

 

 

 

 

Figure 4. Connecting the camera and DVR to the BNC module. 

 

5. Use the F1/PTC1 ÷ F4/PTC4 jumpers to select the type of short circuit / overload protection of individual circuits. 
Jumper in the Fx position – melting fuse activation, PTCx – PTC fuse activation. 
6. Connect the technical outputs to the control panel or other device:

 

- FPS technical output of the PSU status – indicates the voltage loss at any of the outputs (AUX1 ÷ AUX4). 
TAMPER indicating enclosure opening. 
7. Check the optical indication of the PSU status: green LED light on the BNC module. 
8. In case of significant voltage drops on the receivers’ power cables resistance, it is possible to adjust the voltage 
with the ADJ potentiometer (12÷15V DC) 
9. Close the cover after installing and checking the operation of the power supply. 

 
 
 
 
 
 
 
 

 

3.  Power supply operation indication. 

 

3.1. Optical indication. 

The PSU has 6 LED lights at the front panel: 
 

Summary of Contents for GREEN POWER CCTV BNC04124

Page 1: ...BNC04124 v 1 0 BNC 12V 4x1A Switch mode power supply unit for CCTV EN Edition 1 from 26 11 2013 Supersedes the edition BNC GREEN POWER CCTV ...

Page 2: ...puts 4 Service and operation 4 1 Overload or short circuit of the power supply output 4 2 Maintenance 1 Technical description 1 1 General description The PSU BNC04124 is intended for uninterrupted supply of CCTV systems requiring stabilized voltage of 12V DC The output voltage can be adjusted with a potentiometer between 12V and 15V DC The power supply unit enables transmitting power and video usi...

Page 3: ...cuits 4 Jumper to select melting fuse or PTC polymer fuse 5 Green LED L1 L4 voltage indication at the AUX outputs during normal operation these LEDs are on 6 BNC connector of the video output to the DVR 7 BNC connector of the video input from the cameras 8 AUX1 AUX4 camera power supply outputs 12 15V 9 FPS technical output indicating failure OC type 10 FPS technical output indicating failure relay...

Page 4: ... Figure 3 1 4 Technical parameters electrical parameters Table 3 mechanical parameters Table 4 safety of use Table 5 operation parameters Table 6 Electrical parameters Table 3 Mains supply 176 264V AC Current consumption 0 6A 230V AC max PSU s power 48W max Efficiency 80 Output voltage 12V DC The adjustment range of the output voltage 12 15V DC Output current 4x 1 A Ripple voltage 100 mV p p max S...

Page 5: ...E protection circuit O P FG 3000 V AC min 1500 V AC min 500 V AC min Insulation resistance between input circuit and output or protection circuit 100 MΩ 500V DC Operation parameters Table 6 Operating temperature 10ºC 40ºC see Figure1 Storing temperature 20ºC 60ºC Relative humidity 20 90 no condensation Vibrations during operation unacceptable Surges during operation unacceptable Direct insolation ...

Page 6: ...ircuit is UNACCEPTABLE It can cause damage to the equipment or an electric shock 4 Connect the power supply line and video signal to the BNC module See Figure 4 connect the supply voltage of the camera to the AUX1 AUX 4 outputs connect the video signals from the cameras and the DVR to the BNC sockets Figure 4 Connecting the camera and DVR to the BNC module 5 Use the F1 PTC1 F4 PTC4 jumpers to sele...

Page 7: ...re 2 component 5 indicate voltage at the individual outputs of the module L1 for AUX 1 etc Activation of the short circuit overload protection of a given circuit is indicated by turning off one of the Lx LEDs 3 2 Technical outputs The PSU has the following indication outputs FPS technical output of the PSU status OC type output indicating failure short circuit overload During normal operation shor...

Page 8: ...rer 4 The warranty applies to complete equipment accompanied by a properly filled warranty claim with a description of the defect 5 Should the claim be accepted the manufacturer is obliged to provide warranty repairs at the earliest convenience however not later that within 14 days from the delivery to the service centre of the manufacturer 6 The repair period mentioned in point 5 may be prolonged...

Reviews: