2. Installation. 

 

2.1 Requirements. 

             

The buffer PSU shall be mounted by a qualified installer with appropriate  permissions and qualifications 

for 230V/AC installations and low-voltage installations (required and necessary for a given country). The device 
shall be mounted in confined spaces, according to the environment class II, with normal air humidity (RH=90% 
max. without condensation) and the temperature from -

10°C to +40°C. The PSU shall work in a vertical position 

that guarantees sufficient convectional air-flow through ventilating holes of the enclosure. 

 
Before installation, prepare a PSU load balance. During normal operation, the total current drawn 

by the device may not exceed I = 2,2A

*

.  Maximum battery charge current: 0,3A

*

. Total device c 

battery: 2,5A max

*

 
As the PSU is designed for a continuous operation and is not equipped with a power-switch, therefore an 

appropriate  overload  protection  shall  be  guaranteed  in  the  power  supply  circuit.  Moreover,  the  user  shall  be 
informed  about  the  method  of  unplugging  (usually  through  assigning  an  appropriate  fuse  in  the  fuse-box).  The 
electrical system shall follow valid standards and regulations. 
 

2.2 Installation procedure. 

 

1. Before installation, cut off the voltage in the 230V power-supply circuit.

 

2. Mount the PSU in a selected location and connect the wires. 
3. Connect the power cables (~230Vac) to L-N clips of the PSU. Connect the ground wire to the clip marked by the 
earth symbol PE (PSU module connector). Use a three-core cable (with a yellow and green PE protection wire) to 
make the connection. Lead the cables to the appropriate clips through the insulating bushing of the connection 
board. 
 
 

 

The shock protection circuit shall be performed with a particular care, i.e. the yellow and 
green wire coat of the power cable shall stick to one side of the terminal - marked with  

 symbol on the PSU enclosure. Operation of the PSU without the properly made and 

fully  operational  shock  protection  circuit  is  UNACCEPTABLE!  It  can  cause  a  device 
failure or an electric shock. 

 
4. Connect the 

receivers’ cables to the terminals 

V+ (+), V-(-) 

of the PSU module.  

5. Connect the power (~230V) 
6. Connect the battery (mind the colours):   
- battery output (+V):  BAT+ cable / red, 
- battery output (0V):  BAT 

– cable / GND / black. 

7. Check the PSU operation indicator: green LED (green LED on the power supply module). 
8. Check the PSU output voltage: 
- the PSU voltage without load should amount to U=27,6V DC.   
9. After installing and checking proper working, the enclosure can be closed. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

                                                 

*

 

Refer to chart 1

 

Summary of Contents for Green Power HPSB 2524B

Page 1: ...HPSB 2524B v 1 0 HPSB 27 6V 2 2A 2x7Ah Buffer switch mode power supply unit EN Edition 1 from 30 09 2014 Supersedes the edition ...

Page 2: ...at require stabilised voltage of 24V DC 15 The PSU provides voltage of U 27 6V DC with output current of I 2 2A 0 3A for battery charge In case of power decay a battery back up is activated immediately The PSU is constructed based on the switch mode PSU with high energy efficiency The PSU is housed in a metal enclosure colour RAL 9003 which can accommodate two 7Ah 12V batteries A micro switch indi...

Page 3: ...e tab 2 3 green LED indicates AC power 4 potentiometer output voltage adjustment 5 BAT GND battery outputs BAT red GND black 6 TAMPER contact sabotage protection NC 7 Additional connector for LED indication Tab 1 The elements of the PSU Element Fig 2 Description L N L N power supply connector PE PE Protection connector electric shock protection V V DC supply output DC supply output GND Tab 2 Outpu...

Page 4: ...y charge refer to chart 1 Output current tAMB 40 C 1 45A 0 3A battery charge refer to chart 1 Voltage adjustment range 24 28V DC Ripple 120mV p p max Current consumption by PSU systems 75 mA Battery charge current 0 3A max 2x 7Ah 5 Short circuit protection SCP electronic Overload protection OLP U 105 150 of power supply automatic return Battery circuit protection SCP and reverse polarity connectio...

Page 5: ...ables can be led Convectional cooling Operation safety tab 5 Protection class EN 60950 1 2007 I first Protection grade EN 60529 2002 U IP20 Electrical strength of insulation between input and output circuits of the PSU I P O P between input circuit and PE protection circuit I P FG between output circuit and PE protection circuit O P FG 3000 V AC min 1500 V AC min 500 V AC min Insulation resistance...

Page 6: ...andards and regulations 2 2 Installation procedure 1 Before installation cut off the voltage in the 230V power supply circuit 2 Mount the PSU in a selected location and connect the wires 3 Connect the power cables 230Vac to L N clips of the PSU Connect the ground wire to the clip marked by the earth symbol PE PSU module connector Use a three core cable with a yellow and green PE protection wire to...

Page 7: ...he restoration of the voltage takes place immediately after the failure overload is over 4 2 Disconnection of discharged battery The PSU is equipped with the discharged battery disconnection system During the battery assisted operation reducing voltage below 19V at the battery terminals will cause battery disconnection 4 3 Maintenance Any and all maintenance operations may be performed following t...

Page 8: ...ter that within 14 days from the delivery to the service centre of the manufacturer 6 The repair period mentioned in item 5 may be prolonged if there are no technical possibilities to carry out the repairs or if the equipment has been conditionally accepted due to the breaking warranty terms by the claimant 7 All the services rendered by force of the warranty are carried out at the service centre ...