background image

6

7

INSTALLATION AND OPERATION MANUAL SOLAR MODULES Q.MAXX-G3 – Q CELLS

INSTALLATION AND OPERATION MANUAL SOLAR MODULES Q.MAXX-G3 – Q CELLS

Installation Site

Please note the following guidelines that apply to the installation 
site:

• 

Solar modules are not explosion-proof and are not suitable 
for use in explosive environments.

 

Ä

Do not operate solar modules near highly flammable gas and 
vapors (e.g. gas tanks, gas stations).

 

Ä

Do not install modules in enclosed space.

 

Ä

Do not install modules in locations where they may be sub-
merged in water (e.g. floodplains).

 

Ä

Do not use modules as a substitute for the normal roofing 
(e.g. modules are not watertight).

 

Ä

Do not install modules in close proximity to air conditioning 
systems.

 

Ä

Do not install modules above 4,000 m (13120 ft) altitude 
above sea level.

 

Ä

Contact with saline water (e.g. spray water from the sea) and 
salt aggregation on the modules must be avoided.

 

Ä

Do not bring any chemical substance (e.g. oil, solvent etc.) 
into contact with any part of the panel. Only substances, 
which are released by Q CELLS, are allowed to be used during 
installation, operation and maintenance.

 

Ä

Any installation of modules on surfaces of water is prohibited. 
This includes installations on floating as well as pile-based 
platforms. Q CELLS may extend the coverage of its warranty 
to such installations, based on a case by case assessment of 
the system design and location. A prior written consent by 
the warrantor is required in any case.

The solar modules are designed for the following applications:

• 

Operating temperatures from –40 °C to +85 °C 

 

(–40 °F  to  +185 °F).

• 

Pull loads up to max. 4,000 Pa and push loads up to max. 
6,000 Pa (see chapter „Mounting Options“).

• 

Installation using a mounting structure for solar modules.

Prevention of Shadowing Effects

Optimal solar irradiation leads to maximum energy output:

 

Ä

For this reason, install the modules so that they face the sun.

 

Ä

Avoid shadowing (due to objects such as buildings, chimneys 
or trees).

 

Ä

Avoid partial shading (for example through overhead lines, 
dirt, snow).

Mounting Structure Requirements

The Modules shall be installed and operated on mounting structures 
that comply with any applicable laws and stipulations as well as 
with the following:

• 

Conform to the necessary structural requirements.

• 

Compliant with local snow and wind loads.

• 

Properly fastened to the ground, the roof, or the façade.

• 

Forces acting on the module are relayed to the mounting 
substructure.

• 

Ensures sufficient rear ventilation of the module.

• 

Avoid the usage of different metals to prevent contact corrosion.

• 

Allows for stress-free expansion and contraction due to 
temperature fluctuations.

 

Ä

Ensure that no additional forces are applied through the 
mounting system into the module except for the wind and 
snow loads. Additional forces and moments of torque at the 
mounting positions caused by torsions, displacements or 
vibrations in the mounting system are not allowed.

 

Ä

Ensure that the clamps and the mounting frame are com-
patible.

Clamp System Recommendations

Use customary clamps that satisfy the following requirements:

• 

Clamp  width:  ≥ 40 mm.

• 

Clamp height compliant with a 32 mm frame height.

• 

Clamp depth: 7-12 mm. (applicable for all CL clamping mounting 
options at section „2.3 Mounting Options“)

• 

Clamps are not in contact with the front glass.

• 

Clamps do not deform the frame.

• 

Clamps that satisfy the structural requirements based on the 
conditions of the installation site according to the applicable 
regulations and technical standards.

• 

Long-term stable clamps that securely affix the module to 
the mounting frame.

Module Orientation Requirements

• 

Vertical or horizontal installation is permitted.

 

Ä

Ensure that rain and melting snow can run off freely. No water 
accumulation.

 

Ä

Ensure that the drainage holes in the frame are not covered. 
No sealing.

75°

 

Ä

Maintain the permissible angle of inclination.

• 

Minimum angle of inclination: 3°

• 

Inclination angles above 75° may be limited 
by local regulations

 

Ä

Standing water on the modules glass needs to 
be avoided.

Fig. 2: 

Installation options for crystalline Q CELLS modules. All dimensions are given in mm. Also observe the maximum 
 test loads and clamping range as specified on the following page. 
 The illustrated installation options apply for both horizontal and vertical module orientation. 

 

Module 

Clamp 

Subconstruction 

Mounting profile

TYPE OF
INSTALLATION

MODULE

POINT MOUNTING SYSTEM

LINEAR MOUNTING SYSTEM

INSTALLATION 
WITH CLAMPS

Q.MAXX-G3

HYBRID 
CLAMPING

Q.MAXX-G3

INSTALLATION 
ON MOUNTING 
POINTS

Q.MAXX-G3

INSTALLATION 
WITH INSERTION 
PROFILES

Q.MAXX-G3

NOT PERMITTED

2  PLANNING

2.2  REQUIREMENTS

2  PLANNING

2.3  MOUNTING OPTIONS

300 - 450

EUROPE

100 - 250

CL5

720 - 1120

EUROPE

100 - 250

CL6b

720 - 1120

150 - 350

CL6a

CL2a

20 - 300

CL2b

20 - 300

CL2a

20 - 300

CL2b

20 - 300

20 - 550

EUROPE
ASIA

CL1a

20 - 550

150 - 450

CL1b

15 - 210

20 - 550

EUROPE
ASIA

CL1a

20 - 550

150 - 450

CL1b

15 - 210

CL3

CL4

250 - 450

200 - 350

0 - 300

0 - 300

CL3

CL4

CL4

0 - 200

ROW

CL3

200 - 350

IP1

IP2

IP1

IP2

IP1

IP2

IP1

IP2

EN

4 × Mounting 
points

376

FB2

EN

4 x Mounting 
points

376

FB1

Summary of Contents for Q.ANTUM DUO Z

Page 1: ...INSTALLATION AND OPERATION MANUAL Q MAXX G3 solar module series Valid for Africa Europe LatinAmerica South America DRAFT ...

Page 2: ...ipulations such as country specific regulations for pressure equipment operational safety hazardous goods and environmental protection Regulations and requirements specific to the system Any applicable laws and requirements in particular inter national country specific regional laws and stipulations governing the planning installation and operation of solar power systems and work on roofs Any vali...

Page 3: ...ts for solar power systems Ä Please be sure to contact the relevant local authorities and energyprovidersregardingregulationsandpermitrequirements prior to installation of the solar power system Other applicable documents In addition to this Manual following technical information are relevant DOCUMENT TYPE Product data sheet Packaging and transport information Fig 1 External dimensions and compone...

Page 4: ...mounting substructure Ensures sufficient rear ventilation of the module Avoid the usage of different metals to prevent contact corrosion Allows for stress free expansion and contraction due to temperature fluctuations Ä Ensure that no additional forces are applied through the mounting system into the module except for the wind and snow loads Additional forces and moments of torque at the mounting ...

Page 5: ...stem installer is responsible for the determination of location specific load requirements Ä CL1a at high loads 5400 4000Pa The clamp position is variable in the given range but the distance between the clamps along the long side of the module span must not be larger than 1250mm Ä CL1b Using of short mounting rails are permissible if they overlap with the module less than 210mm Minimum height of t...

Page 6: ...y the occurrence of reverse currents caused by module defects ground leaks or defective insulation Ä Ensure that the maximum reverse current load capacity indicated in the data sheet is met In order to limit reverse currents that may occur we recommend using the following safety options 1 Layout with a limited number of parallel connected strings Please refer to the latest revision of AS NZS 5033 ...

Page 7: ...damage may occur Ä Never step on modules Ä Do not subject modules to any mechanical stress Ä Do not allow any objects to fall onto modules 3 INSTALLATION 3 1 SAFETY AND TRANSPORT Danger Risk of fatal injury due to electric shock Ä Block off the installation zone Ä Keep children and unauthorized individuals away from the solar power system Danger Risk of fatal injury due to electric shock Ä Ensure ...

Page 8: ...e separation of a closed circuit These can result in life threatening injuries The danger increases when several modules are connected in series Ä Please be aware of that the entire open circuit voltage is active even at low levels of solar irradiation Ä Pleasefollowthevalidnationalregulationsandsafetyguidelines for the installation of electrical devices and systems Ä Please make sure to take all ...

Page 9: ... page 3 Ä Ensure correct polarity Ä Use solar cables for the connection at the junction box outlet Ä Only interconnect connectors of the same type and manufacturer Ä Use minimum 4mm2 copper wires insulated for a minimum of 90 C for field connections Note Module damage may occur Ä Ensure that the cabling is not under mechanical stress Comply with bending radius of 60mm Ä Ensure that the cables do n...

Page 10: ...al friction Ä Ensure that cables are protected from abrasion tension compression and cutting forces in full accordance with AS NZS 3000 and all other relevant standards 4 ELECTRICAL CONNECTION 4 4 AFTER INSTALLATION Ä No dry cleaning or use of rotating brushes Ä Modules must be cleaned manually and only with sufficient water Protective Grounding Ä The modules must be grounded in accordance with th...

Page 11: ...ductive parts WARNING Risk of falling due to unsecured access Ä Never access the installation area alone or without taking adequate security precautions Ä Please commission a trade specialist NOTE Module surface damage may occur Ä Remove snow and ice carefully without force e g with a very soft broom Ä Do not scratch off dirt Ä Rinse dirt dust leaves etc off with lukewarm water or use only for the...

Page 12: ...on manual solar modules Q MAXX G3_2020 11_Rev01_AU HANWHA Q CELLS AUSTRALIA PTY LTD Suite 1 Level 1 15 Blue Street North Sydney NSW 2060 Australia TEL 61 0 2 9016 3033 FAX 61 0 2 9016 3032 EMAIL q cells australia q cells com WEB www q cells com au DRAFT ...

Reviews: