background image

8

9

INSTALLATION AND OPERATION MANUAL SOLAR MODULES Q.MAXX-G2 – Q CELLS

INSTALLATION AND OPERATION MANUAL SOLAR MODULES Q.MAXX-G2 – Q CELLS

Specifications

MODULE TYPE

MOUNTING
OPTION

POSITION OF 
CLAMPS* [MM]

TEST LOAD  
PUSH/PULL** [PA] 

DESIGN LOAD 
PUSH/PULL** [PA] 

SAFETY  
FACTOR

Q.MAXX-G2

CL1 / CL3

250 - 450

5400/2400

3600/1600

1.5

FB1 / FB2

380

IP1

-

CL1

0 - 250 
450 - 550

2400/2400

1600/1600

CL2a (with rails) /  

CL2b (without rails)

0 - 300

CL4

0 - 300

CL5

short side: 0 - 250
long side: 300 - 450

4000/4000

2670/2670

 

Ä

The below mounting options are only possible under certain conditions.

MODULE TYPE

MOUNTING  
OPTION

POSITION OF 
CLAMPS* [MM]

TEST LOAD  
PUSH/PULL*** [PA] 

DESIGN LOAD 
PUSH/PULL*** [PA] 

SAFETY  
FACTOR

Q.MAXX-G2

IP2

-

2400/2200

1600/1470

1.5


** 
*** 

Distance between outer edge of module and middle of the clamp. 
Loads according to IEC 61215-2:2016 and UL 61730. 
Test procedure according to IEC 61215-2:2016 and UL 61730. Mounting options do not fulfill the requirements of the standards.

ATTENTION

 

Ä

The loads in the table are related to the mechanical stability of the solar modules. The mechanical stability of the mounting 
system including clamps has to be evaluated by the system supplier. The Q CELLS listed test load values were determined 
with the following clamp parameters: clamp width = 40 mm and clamp depth = 10 mm. The system installer is responsible for 
the determination of location-specific load requirements.

 

Ä

Ensure, that the subconstruction does not touch the junction box (even under load). Ensure that the clamps or insertion profiles 
etc. do not touch the glass (even under load).

 

Ä

Ensure, that the connection cables of the junction box do not run between laminate and mounting rails.

 

Ä

Ensure, minimum support depth of 15 mm on the back side of the module for IP1, IP2, CL2b, CL3, CL4 and CL5. Ensure 
minimum support depth of 10 mm on the front side of the module for IP1 and IP2.

 

Ä

CL1, CL2a and CL3 with rails: Ensure that module frame is fixed directly on the rail of the substructure (no spacer allowed 
between the module and substructure).

 

Ä

Module bend under loads. Therefore, sharp objects (e.g. screws) must not be mounted near the module backside.

 

Ä

Use M8 corrosion-proof screws and washers (diameter ≥ 15.8 mm or ≥ 0.62 in) for FB1 and FB2 mounting.

Module Selection

For detailed key electrical data, please refer to the actual data sheet 
referring to the relevant Module (available at www.q-cells.com). 

 

Ä

For maximum energy yields, mismatches of specified elec-
tric current (I

MPP

) of more than 5 % should be avoided for all 

modules connected in series.

Safety Factor

During normal operation, a module may generate a greater current 
and / or higher voltage than that determined under standardised 
test conditions. Please use a safety factor of 1.25 for the following:

• 

Calculating the voltage measurement values (V

OC

) of components 

• 

Calculating the current measurement values (I

SC

) of conductors

• 

Sizing of control systems connected to the outlets of the solar 
modules 

 

Ä

Please follow the valid national guidelines for the installation 
of electrical systems.

 

Ä

Please refer to the latest revision of AS/NZS 5033 (includ-
ing all relevant amendments) and the Clean Energy Council 
Guidelines (for Australia).

Series Connection

Connection of modules in series is only permitted up to the 
maximum system voltage as listed in the applicable data sheet 
of all the relevant modules to be installed.

 

Ä

Take into account all possible operating situations and all 
relevant technical norms and regulations when designing the 
system. It has to be ensured that the maximum system voltage, 
including all necessary safety margins, is not exceeded. 

 

Ä

Take the voltage limit of the inverter into account when 
determining the maximum number of modules in the string.

Parallel Connection

Modules may be damaged by the occurrence of reverse currents 
(caused by module defects, ground leaks, or defective insulation).

 

Ä

Ensure that the maximum reverse current load capacity indi-
cated in the data sheet is met. 

In order to limit reverse currents that may occur, we recommend 
using the following safety options:

1) 

Layout with a limited number of 
parallel connected strings :

Please refer to the latest revision of AS/NZS 5033 (including all 
relevant amendments) for parallel string overcurrent protection 
requirements.

2) 

Layout with string fuses :

Place fuses for each string of modules at the plus and minus ends. 
Use gPV-fuses according to IEC 60269-6. Observe the maximum 
permitted number of strings as indicated in the specifications 
provided by the respective string fuse manufacturer and the 
technical guidelines.

NOTE! 

When installing different product versions, the lowest minimum 
permitted reverse current load capacity applies.  

Inverters

Inverters with or without transformers may be used.

2  PLANNING

2.3  MOUNTING OPTIONS

2  PLANNING

2.4 ELECTRICAL LAYOUT

Summary of Contents for Q MAXX-G2 Series

Page 1: ...INSTALLATION AND OPERATION MANUAL Q MAXX G2 solar module series Valid for Africa Europe LatinAmerica South America...

Page 2: ...tions such as country specific regulations for pressure equipment operational safety hazardous goods and environmental protection Regulations and requirements specific to the system Any applicable law...

Page 3: ...solar power systems Please be sure to contact the relevant local authorities and energyprovidersregardingregulationsandpermitrequirements prior to installation of the solar power system Other applica...

Page 4: ...und the roof or the fa ade Forces acting on the module are relayed to the mounting substructure Ensures sufficient rear ventilation of the module Avoid the usage of different metals to prevent contact...

Page 5: ...eet referring to the relevant Module available at www q cells com For maximum energy yields mismatches of specified elec tric current IMPP of more than 5 should be avoided for all modules connected in...

Page 6: ...o not install damaged modules Inform your distributor of any damages immediately NOTE Module damage may occur Do not stack modules NOTE Module damage may occur Do not install modules near flammable ga...

Page 7: ...ot modify the module e g do not drill any additional holes 3 INSTALLATION 3 2 PREPARATION OF INSTALLATION Option 1 Fasten the module with 4 clamps in the specified clamping range see Fig 2 p 7 Tighten...

Page 8: ...rvals specified by the inverter manufacturer after switching off the inverter Make sure that the plugs can not be connected unintentionally Before working on the contacts check them for safety extra l...

Page 9: ...to rotate some modules 180 Module orientation can clearly be identified from the front side by the serial number and barcode labelled behind the module glass on the side with negative connection cabl...

Page 10: ...by certified personnel The time intervals and extent of the inspection can depend on local circumstances e g salt ammonia content in the air high humidity etc The customer operator must inform himself...

Page 11: ...tion manual solar modules Q MAXX G2_2020 07_Rev03_AU HANWHA Q CELLS AUSTRALIA PTY LTD Suite 1 Level 1 15 Blue Street North Sydney NSW 2060 Australia TEL 61 0 2 9016 3033 FAX 61 0 2 9016 3032 EMAIL q c...

Reviews: