background image

8

9

INSTALLATION AND OPERATION MANUAL SOLAR MODULES Q.PEAK DUO-G10.X – Q CELLS

INSTALLATION AND OPERATION MANUAL SOLAR MODULES Q.PEAK DUO-G10.X – Q CELLS

2  PLANNING

2  PLANNING

2.3  MOUNTING OPTIONS

2.3  MOUNTING OPTIONS

TYPE OF
INSTALLATION

POINT MOUNTING SYSTEM

LINEAR MOUNTING SYSTEM

INSTALLATION 
WITH INSERTION 
PROFILES

NOT PERMITTED

IP1

IP2

IP1

IP2

Specifications

MOUNTING
OPTION

POSITION OF CLAMPS* [MM]

TEST LOAD 
PUSH / PULL**  [PA] 

DESIGN LOAD 
PUSH / PULL**  [PA] 

SAFETY 
FACTOR

CL1a

130 - 350

5400 / 4000

3600 / 2660

1.5

20 - 450

5400 / 3600

3600 / 2400

20 - 650

2400 / 2400

1600 / 1600

CL1b

300 - 500

2400 / 2400

1600 / 1600

CL2a 

(with rails)

20 - 300***

3600 / 2400

2400 / 1600

CL2b

(without rails)

20 - 200

2400 / 2400

1600 / 1600

CL3

240 - 350

4000 / 4000

2660 / 2660

FB1

395.5

5400 / 4000

3600 / 2660

FB2

395.5

4000 / 4000

2660 / 2660

IP1

-

3600 / 3300

2400 / 2200

CL5

short side: 20 - 100
long side: 300 - 450

CL6c

outer clamps: 20 - 400
middle clamps: 640 - 1240***

3600 / 3600

2400 / 2400

CL6d

short side: 20 - 250
long side: 640 - 1240***

4000  / 3600

2660 / 2400


** 
***

Distance between outer edge of module and middle of the clamp; consider further details below.
Loads according to IEC 61215-2:2016 and UL 61730.
Rails must not be under the junction box.

MOIUNTING OPTIONS

REQUIREMENTS

All

 

Ä

The loads in the table are related to the mechanical stability of the solar modules. The 
mechanical stability of the mounting system including clamps has to be evaluated by the system 
supplier. The listed test load values have been determined with the following clamp parameters: 
clamp width = 40 mm and clamp depth = 10 mm.

 

Ä

The system installer is responsible for the determination of location-specific load requi-
rements.

 

Ä

Ensure that the connection cables of the junction box do not run between laminate and 
mounting rails.

 

Ä

Modules bend under load. Therefore, sharp objects (e.g. screws, ballast stones, rail ends, rails 
with burrs or sharp corners) must not be placed near the module backside so as not to touch the 
laminate under load.

 

Ä

Ensure that the junction boxes do not touch the mounting structure (e.g. shorts rails, ballast, etc.) 
or the rooftop under load. Clamps or insertion profiles etc. must not touch the glass (even under 
load).

 

Ä

Unbalanced loads (e.g. snow overhangs, snowdrifts) which result in locally significantly 
increased loads must be removed or avoided by technical measures.

CL1a, CL2a, CL3,

FB1, FB2

 

Ä

Ensure that module frame is fixed directly on the rail of the substructure (no spacer allowed 
between the module and substructure).

CL1a

 

Ä

At push test loads of 5400 Pa: The clamp position is variable in the given range but the 
distance between the clamps along the long side of the module (span) must not be larger than 
1250 mm. 

CL1b

 

Ä

Using of short mounting rails are permissible, if they overlap under the module less than 210 mm. 
Minimum clearance between frame bottom edge and roof top must be ≥ 35 mm. 

CL1b, CL2b, CL3,

FB2, CL6c, CL6d

 

Ä

A minimum support depth of 15 mm is required on the back side of the module. 

CL5

 

Ä

The minimum required support depth on the module backside is 10 mm on long frame side and 
15 mm on short frame side. 

IP1

 

Ä

Ensure minimum support depth of 15 mm on the backside and 10 mm on the front side of the 
module. 

FB1, FB2

 

Ä

Use M8 corrosion-proof screws and washers (diameter ≥ 15.8 mm) for mounting slots (Detail A, 
Fig.1). Mounting screws and washers should have the same material properties.

CL6c, CL6d

 

Ä

Use of short mounting rails under the modules are permissible, if they do not touch the laminate 
under load.

Summary of Contents for Q.PEAK DUO BLK-G10

Page 1: ...INSTALLATION AND OPERATION MANUAL Q PEAK DUO G10 X solar module series Valid for Africa Europe LatinAmerica South America ...

Page 2: ...onal safety hazardous goods and environmental protection Regulations and requirements specific to the system Any applicable laws and requirements in particular inter national country specific regional laws and stipulations governing the planning installation and operation of solar power systems and work on roofs Any valid international national and regional regulations governing work with direct c...

Page 3: ...mation are relevant DOCUMENT TYPE Product data sheet Packaging and transport information External dimensions and components for Q PEAK DUO G10 Q PEAK DUO G10 Q PEAK DUO G10 a Q PEAK DUO G10 a Q PEAK DUO G10 4 Q PEAK DUO G10 4 Q PEAK DUO BLK G10 Q PEAK DUO BLK G10 Q PEAK DUO BLK G10 a Q PEAK DUO BLK G10 a Q PEAK DUO BLK G10 4 and Q PEAK DUO BLK G10 4 DE DETAIL A 16 mm 8 5 mm 21 25 mm 980 mm 1717 mm...

Page 4: ...açade Forces acting on the module are relayed to the mounting substructure Ensures sufficient rear ventilation of the module Avoid the usage of different metals to prevent contact corrosion Allows for stress free expansion and contraction due to temperature fluctuations Ä Ensure that no additional forces are applied through the mounting system into the module except for the wind and snow loads Add...

Page 5: ...ts Ä Ensure that the connection cables of the junction box do not run between laminate and mounting rails Ä Modules bend under load Therefore sharp objects e g screws ballast stones rail ends rails with burrs or sharp corners must not be placed near the module backside so as not to touch the laminate under load Ä Ensure that the junction boxes do not touch the mounting structure e g shorts rails b...

Page 6: ...reverse currents caused by module defects ground leaks or defective insulation Ä Ensure that the maximum reverse current load capacity indicated in the data sheet is met In order to limit reverse currents that may occur we recommend using the following safety options 1 Layout with a limited number of parallel connected strings Withoutundertakingfurthercurrentblockingmeasures amaximum of two module...

Page 7: ...Module damage may occur Ä Never step on modules Ä Do not subject modules to any mechanical stress Ä Do not allow any objects to fall onto modules 3 INSTALLATION 3 1 SAFETY AND TRANSPORT Danger Risk of fatal injury due to electric shock Ä Block off the installation zone Ä Keep children and unauthorized individuals away from the solar power system Danger Risk of fatal injury due to electric shock Ä ...

Page 8: ...eatening injuries The danger increases when several modules are connected in series Ä Please be aware of that the entire open circuit voltage is active even at low levels of solar irradiation Ä Pleasefollowthevalidnationalregulationsandsafetyguidelines for the installation of electrical devices and systems Ä Please make sure to take all necessary safety precautions With module or phase voltages of...

Page 9: ...nel see page 3 Ä Ensure correct polarity Ä Use solar cables for the connection at the junction box outlet Ä Only interconnect connectors of the same type and manufacturer Ä Use minimum 4mm2 copper wires insulated for a minimum of 90 C for field connections Note Module damage may occur Ä Ensure that the cabling is not under mechanical stress Comply with bending radius of 60mm Ä Ensure that the cabl...

Page 10: ... concentrators e g mirrors or lenses Ä Ensure that the cabling is not exposed and or hanging and is protected from dirt moisture and mechanical friction 4 ELECTRICAL CONNECTION 4 4 AFTER INSTALLATION Protective Grounding Ä The modules must be grounded in accordance with the local statutory regulations DANGER Risk of fatal injury due to electric shock Ä Do not attempt to fix any problems yourself e...

Page 11: ...amage may occur Ä Remove snow and ice carefully without force e g with a very soft broom Ä Do not scratch off dirt Ä Module cleaning has to be done by qualified personnel according to the state of the art and taking into account all relevant safety issues and general product properties e g but not restricted to electrical safety mechanical stability load limits depending on the actual mounting opt...

Page 12: ...lee 17 21 06766 Bitterfeld Wolfen Germany TEL 49 0 34946699 23222 FAX 49 0 34946699 23000 EMAIL sales q cells com WEB www q cells com Subject to change without notice Q CELLS Installation manual solar modules Q PEAK DUO G10 X_2021 09_Rev01_EN ...

Reviews: