INSTALLATION AND OPERATION MANUAL SOLAR MODULES Q.PEAK DUO XL-G11S.X / BFG

INSTALLATION AND OPERATION MANUAL SOLAR MODULES Q.PEAK DUO XL-G11S.X / BFG

18

19

0.20 in (5 mm)

0.39 

in 

(10 

mm)

3  Installation

3.3 Module installation

4  Electrical Connection

4.1 Safety

Danger! 
Risk of fatal injury due to electric shock!

When disconnecting an electric circuit carrying direct current, 
electric arcs can occur that may result in life-threatening injuries.

  Do NOT unplug the cable when under load.
  Do NOT connect any exposed cable ends.
  Electrical work may only be performed by qualified and skilled 

personnel (see page 3).

A solar module generates electrical current and voltage even 
at a low intensity of illumination. Sparks and electric arcs may 
result from the separation of a closed circuit. These can result 
in life-threatening injuries. The danger increases when several 
modules are connected in series.

  Please be aware of that the entire open circuit voltage is active 

even at low levels of solar irradiation.

  Please follow the valid national regulations and safety guide-

lines for the installation of electrical devices and systems.

  Please make sure to take all necessary safety precautions. 

With module or phase voltages of more than 120 V, the safety 
extra-low voltage range is exceeded.

  Carry out work on the inverter and the wiring with extreme cau-

tion.

  Ensure that the modules are disconnected at the inverter prior 

to separation.

  Be sure to observe the time intervals specified by the inverter 

manufacturer after switching off the inverter.

  Make sure that the plugs can not be connected unintentionally.
  Before working on the contacts, check them for safety ex-

tra-low voltage.

Danger! Risk of fatal injury due to electric shock!

  Only use dry, insulated tools for electrical work.

Danger! Risk of fatal injury due to electric shock!

  Never touch live contacts with bare hands.
  Cover connectors by suitable protective caps until 

installation.

Danger! Risk of fatal injury due to electric shock!

  Insulate any exposed cable ends.
  Only connect cables with plugs.

Option 1:

  Fasten the module with 4 clamps in the specified 

clamping range, see section "Mounting options with 
clamps" of chapter "2.3 Mounting optoins".

  Tighten clamps according to manufacturer’s instruc-

tions.

  Maintain an interval of at least 0.39 in (10 mm) be-

tween two modules along the short side and  
0.20 in (5 mm) along the long side.

Note! Module damage may occur!

  Do not subject modules to mechanical tension. Max. 

torsion 0.12 in / ft (10 mm / m).

Option 2:

  Install the module at the 4 mounting points,  

see see section “Mounting options with bolts” of 
chapter “2.3 Mounting Options”.

  Tighten screws according to manufacturer’s instruc-

tions.

Danger! Risk of fatal injury due to electric shock!

  Never open the junction box.
  Do not remove bypass diodes.

Summary of Contents for Q.PEAK DUO XL-G11S /BFG Series

Page 1: ...Installation and operation manual Q PEAK DUO XL G11S X BFG solar module series...

Page 2: ...ator are responsible for com pliance with all applicable statutory requirements and regulations The following regulations and standards must be upheld at all times during the installation operation an...

Page 3: ...AGE THIS INCLUDES IMPROPER IN STALLATION OR CONFIGURATION IMPROPER MAINTENANCE UNINTENDED USE AND UNAUTHORIZED MODIFICATION Attention This marking indicates that this product should not be disposed of...

Page 4: ...Installation using a mounting structure for solar modules Mounting Structure Requirements Requirements for the mounting structure Conform to the necessary structural requirements Compliant with local...

Page 5: ...sult from the safety factor 1 5 Mounting options with clamps The illustrated installation options apply for both horizontal and vertical module orientation Module Clamp Mounting rail 4 CLAMPS ON LONG...

Page 6: ...same material properties Distance between outer edge of module and middle of the clamp 2 Planning 2 3 Mounting options Tracker mounting options Module Bolt Mounting rail TRACKER INSTALLATION USING 15...

Page 7: ...clear ance between the bottom module plane level of bottom frame leg and closest substructure element below solar module lam inate The minimum clearance is defined by the maximum test push load and t...

Page 8: ...gulations when designing the system It has to be ensured that the maximum system voltage including all necessary safety margins is not exceeded Take the voltage limit of the inverter into account when...

Page 9: ...connection cables or junction box Carry modules upright and horizontally as shown Note Module damage may occur Never step on modules Do not subject modules to any mechanical stress Do not allow any ob...

Page 10: ...out work on the inverter and the wiring with extreme cau tion Ensure that the modules are disconnected at the inverter prior to separation Be sure to observe the time intervals specified by the invert...

Page 11: ...ectrical work may only be performed by qualified and skilled personnel see page 3 Ensure correct polarity Use solar cables for the connection at the junction box outlet Only interconnect connectors of...

Page 12: ...n inches 0 1 7 7 0 0 0 8 0 0 08 0 79 0 47 0 08 Option A Use of a grounding lug A listed grounding lug can be bonded to the frame using the grounding holes pre drilled in the frame These holes are mark...

Page 13: ...installation area alone or without taking ade quate security precautions Please commission a trade specialist NOTE Module surface damage may occur Remove snow and ice carefully without force e g with...

Page 14: ...nstallation manual solar modules Q PEAK DUO XL G11S X BFG_modules_series_2023 10_Rev05_NA HANWHA Q CELLS AMERICA INC 400 Spectrum Center Drive Suite 1400 Irvine CA 92618 USA EMAIL WEB TEL hqc inquiry...

Reviews: