  Inspect the packaging for damages.
  Contact the transport company regarding any dam-

age to the packaging and follow their instructions.

  Follow any instructions on the packaging.

2  Planning

2.4 Electrical layout

Module Selection

For detailed key electrical data, please refer to the actual data 
sheet referring to the relevant Module (available at www.qcells.
com).

  For maximum energy yields, mismatches of specified electric 

current (I

MPP

) of more than 5 % should be avoided for all mod-

ules connected in series.

Safety Factor

During normal operation, a module may generate a greater cur-
rent and / or higher voltage than that determined under standard-
ized test conditions. Accordingly, the values of I

SC

 and V

OC

 marked 

on the module should be multiplied by a facot of 1.25 when de-
termining:

 

the component voltage ratings,

 

conductor ampacities,

 

fuse sizes,

 

size of controls connected to the PV output.

Refer to Section 690-8 of the National Electrical Code for an 
additional multiplying factor of 125 percent (80 percent derating) 
which might be applicable.

  Please follow the valid national guidelines for the installation of 

electrical systems (refer to section 690-8 of the NEC for an ad-
ditional multiplying factor of 125 percent [80 percent derating] 
which may be applicable).

Series Connection

Connection of modules in series is only permitted up to the maxi-
mum system voltage as listed in the applicable data sheet.

  Take into account all possible operating situations and all rel-

evant technical norms and regulations when designing the 
system. It has to be ensured that the maximum system voltage, 
including all necessary safety margins, is not exceeded.

  Take the voltage limit of the inverter into account when deter-

mining the maximum number of modules in the string.

Parallel Connection

Modules may be damaged by the occurrence of reverse currents 
(caused by module defects, ground leaks, or defective insulation).

  Ensure that the maximum reverse current load capacity indicat-

ed in the data sheet is met.

In order to limit reverse currents that may occur, we recommend 
using the following safety options:

1)  Layout with a limited number of parallel connected strings :

Without undertaking further current blocking measures, a maxi-
mum of two module strings may be operated in parallel on a sin-
gle inverter or MPP tracker.

2)  Layout with string fuses :

Use overcurrent devices (e.g. fuses) according to the relevant 
standards in each string. Use gPV-fuses according to IEC 60269-
6. Observe the maximum permitted number of strings as indicat-
ed in the specifications provided by the respective string fuse 
manufacturer and the technical guidelines.

NOTE!

When installing different product versions, the lowest minimum 
permitted reverse current load capacity applies.

Inverters

Inverters with or without transformers may be used.

3  Installation

3.1 Safety and transport

  Leave modules in their original packaging until instal-

lation.

  Store the modules securely in cool and dry rooms. 

The packaging is not weatherproof.

  Ensure that all personnel are aware of and adhere to 

accident-prevention and safety regulations.

  While working wear clean gloves.

§

GB

§

I

§

D

Danger! Risk of fatal injury due to electric shock!

  Do not install damaged modules.
  Inform your distributor of any damages immediately.

Warning! Fire Risk!

  Do not install modules indoors.
  Do not install modules on moving objects.

Summary of Contents for Q.PEAK DUO XL-G11S /BFG Series

Page 1: ...Installation and operation manual Q PEAK DUO XL G11S X BFG solar module series...

Page 2: ...ator are responsible for com pliance with all applicable statutory requirements and regulations The following regulations and standards must be upheld at all times during the installation operation an...

Page 3: ...AGE THIS INCLUDES IMPROPER IN STALLATION OR CONFIGURATION IMPROPER MAINTENANCE UNINTENDED USE AND UNAUTHORIZED MODIFICATION Attention This marking indicates that this product should not be disposed of...

Page 4: ...Installation using a mounting structure for solar modules Mounting Structure Requirements Requirements for the mounting structure Conform to the necessary structural requirements Compliant with local...

Page 5: ...sult from the safety factor 1 5 Mounting options with clamps The illustrated installation options apply for both horizontal and vertical module orientation Module Clamp Mounting rail 4 CLAMPS ON LONG...

Page 6: ...same material properties Distance between outer edge of module and middle of the clamp 2 Planning 2 3 Mounting options Tracker mounting options Module Bolt Mounting rail TRACKER INSTALLATION USING 15...

Page 7: ...clear ance between the bottom module plane level of bottom frame leg and closest substructure element below solar module lam inate The minimum clearance is defined by the maximum test push load and t...

Page 8: ...gulations when designing the system It has to be ensured that the maximum system voltage including all necessary safety margins is not exceeded Take the voltage limit of the inverter into account when...

Page 9: ...connection cables or junction box Carry modules upright and horizontally as shown Note Module damage may occur Never step on modules Do not subject modules to any mechanical stress Do not allow any ob...

Page 10: ...out work on the inverter and the wiring with extreme cau tion Ensure that the modules are disconnected at the inverter prior to separation Be sure to observe the time intervals specified by the invert...

Page 11: ...ectrical work may only be performed by qualified and skilled personnel see page 3 Ensure correct polarity Use solar cables for the connection at the junction box outlet Only interconnect connectors of...

Page 12: ...n inches 0 1 7 7 0 0 0 8 0 0 08 0 79 0 47 0 08 Option A Use of a grounding lug A listed grounding lug can be bonded to the frame using the grounding holes pre drilled in the frame These holes are mark...

Page 13: ...installation area alone or without taking ade quate security precautions Please commission a trade specialist NOTE Module surface damage may occur Remove snow and ice carefully without force e g with...

Page 14: ...nstallation manual solar modules Q PEAK DUO XL G11S X BFG_modules_series_2023 10_Rev05_NA HANWHA Q CELLS AMERICA INC 400 Spectrum Center Drive Suite 1400 Irvine CA 92618 USA EMAIL WEB TEL hqc inquiry...

Reviews: