background image

INSTALLATION AND OPERATION MANUAL SOLAR MODULES Q.PEAK DUO XL-G11S.X / BFG

INSTALLATION AND OPERATION MANUAL SOLAR MODULES Q.PEAK DUO XL-G11S.X / BFG

8

9

2  Planning

2.3 Mounting options

REQUIREMENTS OF ALL MOUNTING OPTIONS

  The loads in the table are related to the mechanical stability of the solar modules. The mechanical stability of the mounting system 

including clamps has to be evaluated by the system supplier. The listed test load values have been determined with the following 
clamp parameters: clamp width = 1.57 in (40 mm) and clamp depth = 0.39 in (10 mm).

  The system installer is responsible for the determination of location-specific load requirements.
  Ensure that the connection cables of the junction box do not run between laminate and mounting rails. 
  Modules bend under load. Therefore, sharp objects (e.g. screws, ballast stones, rail ends, rails with burrs or sharp corners) must 

not be placed near the module backside so as not to touch the laminate under load.

  Ensure that the junction boxes do not touch the mounting structure (e.g. shorts rails, ballast, etc.) or the rooftop under load. 
  Clamps or insertion profiles etc. must not touch the glass (even under load).
  Unbalanced loads (e.g. snow overhangs, snowdrifts) which result in locally significantly increased loads must be removed or 

avoided by technical measures.

  A minimum support depth of 0.59 in (15 mm) is required on the back side of the module.

Loads according to IEC 61215-2:2016 and UL 61730-2:2017 except for design loads lower than 1600 Pa which do 
not fulfill the requirements of the standards. The test procedure is always according to IEC 61215-2:2016. 
Design loads result from the safety factor 1.5.

Mounting options with clamps

The illustrated installation options apply for both horizontal and vertical module orientation.

Module

Clamp

   Mounting rail

4 CLAMPS ON LONG SIDE & 

2 CONTINUOUS RAILS PARALLEL TO SHORT SIDE

4 CLAMPS ON LONG SIDE (SHORT RAILS ALLOWED)

CL1a

L

CL1b

L

0.59 - 4.33
(15 - 110)

POSITION OF 
CLAMPS* [in]

TEST LOAD 
PUSH / PULL [Pa]

DESIGN LOAD 
PUSH / PULL [Pa]

POSITION OF 
CLAMPS* [in]

TEST LOAD 
PUSH / PULL [Pa]

DESIGN LOAD 
PUSH / PULL [Pa]

L

15.8 - 21.7
(400 - 550 mm)

3600 / 2400

2400 / 1600

L

7.9 - 21.7
(200 - 550 mm)

2100 / 2400

1400 / 1600

CL1a

  These mounting options are not recommended as mounting rails will cast shade on the module rear side. 
  Ensure that module frame is fixed directly on the rail of the substructure (no spacer allowed between the 

module and  substructure).

CL1b

  Using of short mounting rails are permissible, if they overlap with the module less than 4.33 in (110 mm).

Maintain a minimum distance (clearance) of ≥ 1.38 in (35 mm) between frame bottom edge and roof top or 
ballast.

*

Distance between outer edge of module and middle of the clamp.

 4 CLAMPS ON LONG SIDE & 

2 CONTINUOUS RAILS UNDERNEATH LONG FRAME PARTS

2 CLAMPS ON LONG SIDE, 2 CLAMPS ON SHORT SIDE

CL3

L

CL5

L

S

POSITION OF 
CLAMPS* [in]

TEST LOAD 
PUSH / PULL [Pa]

DESIGN LOAD 
PUSH / PULL [Pa]

POSITION OF 
CLAMPS* [in]

TEST LOAD 
PUSH / PULL [Pa]

DESIGN LOAD 
PUSH / PULL [Pa]

L

15.8 - 21.7
(400 - 550 mm)

3600 / 2400

2400 / 1600

S

0.79 (20 mm)

2400 / 2400

1600 / 1600

L

27.6 (700 mm)

CL3

  Ensure that module frame is fixed directly on the rail of the substructure (no spacer allowed between the 

module and substructure).

  Minimum support depth of 0.59 in (15 mm) is required on the back side of the module.

CL5

  Minimum required support depth on the module backside is 0.39 in (10 mm) on long frame side and 0.59 in 

(15 mm) on short frame side.

*

Distance between outer edge of module and middle of the clamp.

Summary of Contents for Q.PEAK DUO XL-G11S /BFG Series

Page 1: ...Installation and operation manual Q PEAK DUO XL G11S X BFG solar module series...

Page 2: ...ator are responsible for com pliance with all applicable statutory requirements and regulations The following regulations and standards must be upheld at all times during the installation operation an...

Page 3: ...AGE THIS INCLUDES IMPROPER IN STALLATION OR CONFIGURATION IMPROPER MAINTENANCE UNINTENDED USE AND UNAUTHORIZED MODIFICATION Attention This marking indicates that this product should not be disposed of...

Page 4: ...Installation using a mounting structure for solar modules Mounting Structure Requirements Requirements for the mounting structure Conform to the necessary structural requirements Compliant with local...

Page 5: ...sult from the safety factor 1 5 Mounting options with clamps The illustrated installation options apply for both horizontal and vertical module orientation Module Clamp Mounting rail 4 CLAMPS ON LONG...

Page 6: ...same material properties Distance between outer edge of module and middle of the clamp 2 Planning 2 3 Mounting options Tracker mounting options Module Bolt Mounting rail TRACKER INSTALLATION USING 15...

Page 7: ...clear ance between the bottom module plane level of bottom frame leg and closest substructure element below solar module lam inate The minimum clearance is defined by the maximum test push load and t...

Page 8: ...gulations when designing the system It has to be ensured that the maximum system voltage including all necessary safety margins is not exceeded Take the voltage limit of the inverter into account when...

Page 9: ...connection cables or junction box Carry modules upright and horizontally as shown Note Module damage may occur Never step on modules Do not subject modules to any mechanical stress Do not allow any ob...

Page 10: ...out work on the inverter and the wiring with extreme cau tion Ensure that the modules are disconnected at the inverter prior to separation Be sure to observe the time intervals specified by the invert...

Page 11: ...ectrical work may only be performed by qualified and skilled personnel see page 3 Ensure correct polarity Use solar cables for the connection at the junction box outlet Only interconnect connectors of...

Page 12: ...n inches 0 1 7 7 0 0 0 8 0 0 08 0 79 0 47 0 08 Option A Use of a grounding lug A listed grounding lug can be bonded to the frame using the grounding holes pre drilled in the frame These holes are mark...

Page 13: ...installation area alone or without taking ade quate security precautions Please commission a trade specialist NOTE Module surface damage may occur Remove snow and ice carefully without force e g with...

Page 14: ...nstallation manual solar modules Q PEAK DUO XL G11S X BFG_modules_series_2023 10_Rev05_NA HANWHA Q CELLS AMERICA INC 400 Spectrum Center Drive Suite 1400 Irvine CA 92618 USA EMAIL WEB TEL hqc inquiry...

Reviews: