2 Planning

2.4 Electrical layout

Module Selection

For detailed key electrical data, please refer to the actual data 

sheet referring to the relevant Module (available at www.qcells.

com/au/).

  For maximum energy yields, mismatches of specified electric 

current (I

MPP

) of more than 5 % should be avoided for all 

modules connected in series.

Safety Factor

During normal operation, a module may generate a greater current 

and / or higher voltage than that determined under standardized 

test conditions. Please use a safety factor of 1.25 for the following:

 

Calculating the voltage measurement values (V

OC

) of 

components

 

Calculating the current measurement values (I

SC

) of conductors

 

Sizing of control systems connected to the outlets of the solar 

modules

  Please follow the valid national guidelines for the installation of 

electrical systems.

  Prefer to the latest revision of AS / NZS 5033 (including 

all relevant amendments) and the Clean Energy Council 

Guidelines (for Australia).

Series Connection

Connection of modules in series is only permitted up to the 

maximum system voltage as listed in the applicable data sheet of 

all the relevant modules to be installed.

  Take into account all possible operating situations and all 

relevant technical norms and regulations when designing the 

system. It has to be ensured that the maximum system voltage, 

including all necessary safety margins, is not exceeded.

  Take the voltage limit of the inverter into account when 

determining the maximum number of modules in the string.

Parallel Connection

Modules may be damaged by the occurrence of reverse currents 

(caused by module defects, ground leaks, or defective insulation).

  Ensure that the maximum reverse current load capacity 

indicated in the data sheet is met.

In order to limit reverse currents that may occur, we recommend 

using the following safety options:

1) Layout with a limited number of parallel connected strings :

Please refer to the latest revision of AS / NZS 5033 (including all 

relevant amendments) for parallel string overcurrent protection 

requirements.

2) Layout with string fuses :

Use overcurrent devices (e.g. fuses) according to the relevant 

standards in each string. Use gPV-fuses according to IEC 

60269-6. Observe the maximum permitted number of strings as 

indicated in the specifications provided by the respective string 

fuse manufacturer and the technical guidelines.

NOTE!

When installing different product versions, the lowest minimum 

permitted reverse current load capacity applies.

Inverters

Inverters with or without transformers may be used.

3 Installation

3.1 Safety and transport

  Leave modules in their original packaging until 

installation.

  Store the modules securely in cool and dry rooms. 

The packaging is not weatherproof.

  Inspect the packaging for damages.

  Contact the transport company regarding  

any damage to the packaging and follow their 

instructions.

  Follow any instructions on the packaging.

Warning! Fire Risk!

  Do not install modules indoors.

  Do not install modules on moving objects.

  Ensure that all personnel are aware of and adhere to 

accident-prevention and safety regulations.

  While working wear clean gloves.

§

GB

§

I

§

D

Danger! Risk of fatal injury due to electric shock!

  Do not install damaged modules.

  Inform your distributor of any damages immediately.

Summary of Contents for Q.MAXX-G5 Series

Page 1: ...Installation and operation manual Q MAXX G5 solar module series...

Page 2: ...le stipulations such as country specific regulations for pressure equipment operational safety hazardous goods and environmental protection Regulations and requirements specific to the system Any appl...

Page 3: ...ED WARRANTY AND MAY CREATE A SAFETY HAZARD AND RISK PROPERTY DAMAGE THIS INCLUDES IMPROPER INSTALLATION OR CONFIGURATION IMPROPER MAINTENANCE UNINTENDED USE AND UNAUTHORIZED MODIFICATION 2 Planning 2...

Page 4: ...he roof or the fa ade Forces acting on the module are relayed to the mounting substructure Ensures sufficient rear ventilation of the module Avoid the usage of different metals to prevent contact corr...

Page 5: ...ues have been determined with the following clamp parameters clamp width 40mm and clamp depth 10mm The system installer is responsible for the determination of location specific load requirements Ensu...

Page 6: ...number of modules in the string Parallel Connection Modules may be damaged by the occurrence of reverse currents caused by module defects ground leaks or defective insulation Ensure that the maximum...

Page 7: ...es or junction box Carry modules upright and horizontally as shown Note Module damage may occur Never step on modules Do not subject modules to any mechanical stress Do not allow any objects to fall o...

Page 8: ...s may result from the separation of a closed circuit These can result in life threatening injuries The danger increases when several modules are connected in series Please be aware of that the entire...

Page 9: ...rformed by qualified and skilled personnel see page 3 Ensure correct polarity Use solar cables for the connection at the junction box outlet Only interconnect connectors of the same type and manufactu...

Page 10: ...l Do not disconnect modules by yourself Please contact an installer or Qcells Technical Customer Service Department Dispose of modules in accordance with the local disposal regulations Ensure that all...

Page 11: ...Remove snow and ice carefully without force e g with a very soft broom Do not scratch off dirt Module cleaning has to be done by qualified personnel according to the state of the art and taking into a...

Page 12: ...cells Installation manual solar modules Q MAXX G5_2023 03_Rev02_AU HANWHA Q CELLS AUSTRALIA PTY LTD Suite 1 Level 1 15 Blue Street North Sydney NSW 2060 Australia EMAIL WEB TEL inquiry aus qcells com...

Reviews: