6.
With the shims and anchor bolts in place, tighten
by securing the nut to the base then turning 2 -3
full turns clockwise. DO NOT use an impact
wrench for this procedure. ( See Fig.
4 )
STEP 5
(Mounting The OFFSIDE column)
Position the OFFSIDE column at the designated
chalk locations and secure to the floor following the
same procedures as outlined in STEP FOUR.
NOTE:
To ease installation of the top beam on
CLEARFLOOR models, it helps to keep the
anchor bolts loose on one of the columns
until
the top beam is mounted
.
STEP 6
(Mounting the OVERHEAD BEAM.)
Using a lifting device, raise the OVERHEAD beam
in position on top of the columns. Bolt to the columns
using the 3/8” x 40 Hex Bolts, Nuts and Washers. (
See Fig. 5 )
NOTE: Limit Switch is on side of
the Powerside Column.
STEP 7
( Mounting The HYDRAULIC POWER UNIT )
Attach the power unit to the POWERSIDE
COLUMN using four 5/16" hex bolts and lock nuts
supplied. Fill the reservoir with 3.5 gallons 10 L.
HYDRAULIC OIL OR DEXRON TYPE III ATF.
Make sure the funnel used to fill the power unit is
clean. (
NOTE
:
The hydraulic oil must be clean, if
not ,the filtrated oil is needed. Or it may cause
damage to power unit and jam to hydraulic cylinder.
( See Fig. 6 )