Page 32
7039-131H
May 5, 2011
R
2100 Millennium Wood Stove (ACC)
G. Tube Channel Assembly Replacement
Removing Tube Channel Assembly
1. Remove the right side shield by removing 2 screws in the
back using a Phillips head screw driver.
2. Remove 4 screws from channel access cover and remove
cover.
3. Locate 2 channel nuts inside of chamber and remove
using a 7/16 socket wrench. Slide out tube channel
assembly.
NOTE
: Soak the bolts with penetrating oil for at least 15 min-
utes before trying to remove them.
Replacing Tube Channel Assembly
1. Slide one gasket on each tube first
2. Slide the tube channel assembly into side of firebox and
insert each tube into the corresponding hole in the tube
channel rack starting with the back hole first.
3. Make sure tube channel assembly is flush against the
side of the stove and secure with channel nuts.
4. Re-install channel cover and side shield.
Tube Channel Rack
Channel
Access
Cover
Channel Cover
Screws (4)
Channel
Nuts (2)
Tube Channel
Assembly
Side Panel
Remove
2 Screws
Slide one gasket
over each tube
Figure 32.1
NOTE: Service Space
In order to replace the tube channel assembly a clear-
ance of 17 inches (432mm) is required on the right side
of stove in order to remove the tubes with the stove in
place.
If space is not available, the stove will have to be dis-
connected from the chimney to proceed with the tube
replacement.
Summary of Contents for 21M-ACC
Page 40: ...Page 40 7039 131H May 5 2011 R 2100 Millennium Wood Stove ACC D Homeowner s Notes...
Page 41: ...May 5 2011 7039 131H Page 41 2100 Millennium Wood Stove ACC R D Homeowner s Notes...
Page 42: ...Page 42 7039 131H May 5 2011 R 2100 Millennium Wood Stove ACC E Warranty Policy...
Page 43: ...May 5 2011 7039 131H Page 43 2100 Millennium Wood Stove ACC R...